28 Sep, 2026Executive summary
Advanced Butcherbird Expansion Project (BBX) from feasibility to full project delivery, targeting mechanical completion and commissioning in Q1 CY2027.
Secured AU$28 million in equity placements and progressed a AU$50 million NAIF senior debt facility to strengthen the balance sheet.
Signed a binding offtake agreement for 100% of manganese concentrate with OM Holdings subsidiary, supporting long-term sales.
Revised US$166 million grant agreement with the US Department of Energy for the HPMSM project in Louisiana, aligning with updated execution strategy.
Initiated review and optimisation of the HPMSM Project in the USA to reflect evolving battery market dynamics.
Financial highlights
No revenue recognized for FY2026 due to no ore shipments; prior year revenue was $1.88 million.
Operating loss after tax of $2.14 million, improved from $5.87 million loss in FY2025.
Cash balance at 30 June 2026 was $18.28 million, up from $2.16 million at prior year-end.
Other income of $1.18 million, up from $0.80 million in FY2025.
General and administration expenses reduced to $1.67 million from $3.16 million year-over-year.
Outlook and guidance
BBX remains on track for mechanical completion and commissioning in Q1 CY2027.
Focused on recommencing mining operations and advancing the HPMSM processing facility in the USA.
Continued evaluation of further HPMSM production sites, including in Japan.
Latest events from Element 25
- Butcherbird expansion and US HPMSM project advance on schedule with robust funding and DOE support.E25
Q4 2026 TU - Butcherbird expansion and HPMSM refinery advance, with funding and contracts on track.E25
Q3 2026 TU - Butcherbird expansion and US HPMSM project advanced, despite FY24 revenue and margin declines.E25
H2 2024 - Expansion and US battery materials facility advanced, with improved loss and strong funding.E25
H1 2026 - Expanding Australian manganese mine and US refinery target global battery and steel markets.E25
Investor presentation - BBX expansion and US HPMSM refinery progress, with robust funding and approvals.E25
Q2 2026 TU - US$166M DOE grant, AU$50M NAIF debt, and resource upgrades drive future growth.E25
H2 2025 - Raised AU$10M equity, secured AU$50M debt, and advanced global HPMSM projects; cash AU$10.19M.E25
Q1 2026 TU - Major mine and U.S. refinery expansion advance to meet surging EV battery manganese demand.E25
Investor Update