Investor presentation
Logotype for Element 25 Limited

Element 25 (E25) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Element 25 Limited

Investor presentation summary

29 Oct, 2026

Butcherbird resource and expansion

  • Butcherbird has a 274Mt resource at 10.0% Mn and a 101.4Mt reserve at 10.4% Mn, supporting an 18.3-year mine life; the reserve uses ~40% of the resource.

  • Expansion targets 1.1Mtpa concentrate at 31.6% Mn from 6.1Mtpa ore mining.

  • 2025 feasibility metrics include A$561M pre-tax real NPV, A$379M post-tax real NPV, 96% pre-tax IRR and A$64.8M capital cost.

  • Surface ore, low strip ratio, no explosives or dewatering, and water as the sole reagent underpin the low-impact operating approach.

  • The project is fully permitted and construction-ready, with existing infrastructure and an estimated ~12-month construction period.

Construction and delivery

  • Early site works are complete, including earthworks, process-water pond and pipelines, operations-centre relocation, and site services.

  • Major equipment packages were awarded and ordered; mining, haulage, engineering, offtake and camp agreements were complete as of October 2026.

  • Detailed engineering was well advanced, with long-lead crusher and logwasher orders placed and operational-readiness work progressing.

  • Mechanical completion is targeted for Q1 2027; a binding 100% take-or-pay offtake agreement with OMH was noted in August 2026.

Manganese market and HPMSM strategy

  • China accounts for 95% of HPMSM production, while manganese refining is identified as a key supply-chain bottleneck.

  • GM’s Gen IV EV platform is planned to use LMR; LMR cells are cited as offering 33% greater energy density than LFP at comparable cost.

  • Plans call for a 65,000tpa U.S. battery-grade HPMSM facility with GM and Stellantis; development is subject to financing and permitting.

  • A US$166M U.S. Department of Energy grant supports the Louisiana project and its domestic battery-material supply chain.

  • The process is designed to use fewer reagents, lower emissions and eliminate waste residues and toxic fluorine reagents; Japan and other global markets are also targeted for future capacity.