Ferrovial (FER) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
15 Nov, 2026Project scope and phasing
Phase 1 is a committed 23-mile, westbound, two-lane Express Lanes project; construction cost $8.9bn and proposed concession payment $23.6bn, excluding $515m for State Cost reimbursement at Financial Close.
Phase 2 is a committed 23-mile, eastbound, two-lane project; expected Financial Close 2029 and opening 2036, with construction cost adjustable for inflation under defined contractual parameters.
Indicative Phase 3 covers 14 miles in both directions on I-285 and SR 141; scope, economics and timing remain subject to CDA development, with expected Financial Close 2032 and opening 2040.
Phases 2 and 3 are developed through the CDA and executed under separate phase agreements; the development period runs up to 10 years or until the last Phase Agreement is executed.
Corridor demand and market
I-285E carries 200–240k vehicles daily; congestion lasts 8 hours per day, with 4–5 hours of peak congestion by direction and peak speeds of 20 mph.
Less than 3% of trips are end-to-end; average trip length is 5 miles, and enhanced connectivity could serve 95% of corridor trips.
Trucks represent 10–12% of I-285E traffic versus 3% on SR 400; congestion extends across more hours and both directions on I-285E.
Metro Atlanta population was 6.5m in 2025; median household income was $92k in 2024, 13% above the U.S. average, and the region has 14 Fortune 500 headquarters.
Atlanta’s population, real income per capita and real GDP are forecast to grow at 1.1%, 1.9% and 2.6% CAGRs, respectively, over 2025–34; corridor traffic has been constrained by congestion.
Connectivity and pricing
TEMG’s design increases allowable movements from 42 to 117 and entries/exits per mile from 2.3 to 3.1; it targets 95% of corridor trips served versus 55% in the GDOT reference design.
The design adds or enhances 48 connections, including full freeway-to-freeway connectivity at SR 400 and I-85; in-scope trips increase 1.7x.
Initial Operational Toll Rate soft cap is $2.01/mile in 2025 dollars, with a $4.02/mile hard cap; real-time tolls can rise to 2x OTR when volume exceeds 1,500 PCE/lane/hour or speed falls below 55 mph.
OTR has a 2% annual floor and may adjust for service performance; extended vehicles can pay up to 5x the toll, while large trucks are excluded from Express Lanes.
Latest events from Ferrovial
- North American toll roads anchor infrastructure growth, cash generation and shareholder returns.FER
Investor presentation - 9M growth and record construction backlog, with JFK delivery and traffic risks in focus.FER
Q3 2026 - I-24 Choice Lanes advances under a 50-year concession, with first-phase service targeted for 2034.FER
Status update - Strong H1 2026 growth in revenue and EBITDA, led by North American highways and construction.FER
Q2 2026 - Strong financial results, strategic asset moves, and all proposals approved at the AGM.FER
AGM 2025 - Strong 2025 results, all proposals approved, with major dividends and sustainability focus.FER
AGM 2026 - Double-digit growth in highways, record order book, and strong liquidity drove H1 2025 results.FER
Q2 2025 - H1 2024 net profit surged to €518M on strong toll roads, asset sales, and reduced net debt.FER
Q2 2024 - Q1 2025 delivered double-digit EBITDA growth, strong cash, and major project advances.FER
Q1 2025