First Quantum Minerals (FM) Q2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2025 earnings summary
4 Nov, 2025Executive summary
Q2 2025 copper production was 91,069 tonnes, down 9% from Q1 2025 due to lower grades in Zambia.
Revenue rose 3% quarter-over-quarter to $1.2 billion, driven by higher realized copper and gold prices and increased gold and nickel sales volumes.
EBITDA increased 6% sequentially to $400 million, with net earnings of $18 million, a $41 million improvement.
Government of Panama approved the Preservation and Safe Management (P&SM) Plan for Cobre Panamá, enabling concentrate exports and power plant restart preparations.
Kansanshi S3 Expansion is in final commissioning, on budget and schedule for first production in H2 2025; new near-surface gold zone identified.
Financial highlights
Q2 2025 sales revenue was $1,226 million, gross profit $351 million, and EBITDA $400 million.
Net debt decreased by $334 million to $5,453 million, supported by copper prepayment and strong EBITDA.
Liquidity at June 30, 2025, was $1.7 billion, including $737 million cash and $930 million undrawn revolver.
Adjusted earnings per share were $0.02, compared to $0.00 in Q1 2025 and $(0.02) in Q2 2024.
Cash flows from operating activities were $780 million, up $637 million sequentially, aided by a $500 million copper prepayment.
Outlook and guidance
2025 production guidance remains unchanged: copper 380,000–440,000 tonnes, gold 135,000–155,000 ounces, nickel 15,000–25,000 tonnes.
Kansanshi S3 Expansion and Sentinel initiatives expected to support stronger H2 2025 performance; first production at S3 in H2 2025.
Capital expenditure is expected to decline as S3 Expansion nears completion; 2025 capex guidance is $1.3–$1.45 billion.
Copper and gold hedging programs protect a significant portion of planned production through 2026.
Cobre Panamá power plant restart expected in Q4 2025; P&SM costs to rise to $17–$18 million/month.
Latest events from First Quantum Minerals
- Q4 2025 saw improved profits, Kansanshi S3 ramp-up, and enhanced financial flexibility.FM
Q4 202511 Feb 2026 - Q2 2024 delivered higher copper output and profits, but Cobre Panamá remains suspended.FM
Q2 20243 Feb 2026 - Copper output and earnings surged in Q3 2024, but Cobre Panamá remains suspended.FM
Q3 202419 Jan 2026 - Q3 2025 delivered higher production, improved liquidity, and Kansanshi S3 ramped up ahead of plan.FM
Q3 202515 Jan 2026 - Record copper output, board renewal, and all resolutions approved amid Cobre Panamá challenges.FM
AGM 20258 Jan 2026 - Copper and gold output beat guidance, but revenue fell and risks remain amid Cobre Panamá suspension.FM
Q4 20248 Jan 2026 - Net loss of $23M in Q1 2025; Kansanshi S3 Expansion and liquidity initiatives advanced.FM
Q1 202521 Dec 2025 - $1B gold stream boosts annual deliveries, liquidity, and portfolio diversification.FM
Status Update23 Nov 2025