Frontier Energy (FHE) Q3 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Frontier Energy Limited

Q3 2026 TU earnings summary

30 Oct, 2026

Executive summary

  • Stage One entered construction after Monford mobilised; all material contracts are executed on fixed-price, lump-sum terms.

  • The quarter’s milestones included credit-approved project debt underwriting of up to ~$280 million, a completed $110 million equity raising and a $75.1 million closing cash balance.

Financial highlights

  • Stage One development spend was $27.9 million in the quarter; cash and cash equivalents at quarter-end were $75.132 million.

  • Operating cash outflow was $2.643 million; investing cash outflow was $27.823 million and financing cash inflow was $97.898 million.

  • Updated average annual Stage One forecasts through 30 September 2032 are revenue ~$76 million, EBITDA ~$66 million and free cash flow ~$38 million.

Outlook and guidance

  • First generation is scheduled for 2028; major construction works are due to begin later in 2026, with solar balance-of-plant construction scheduled to commence in early 2027.

  • Financial close is expected in November 2026; first debt drawdown is scheduled for the March quarter of 2027.

  • Stage Two is targeted as a 130MW solar facility with an 80MW, ~8-hour BESS.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Frontier Energy