G Mining Ventures (GMIN) AGM 2026 presentation summary
Event summary combining transcript, slides, and related documents.
AGM 2026 presentation summary
13 Aug, 2026Strategic growth and project execution
Advancing a portfolio of high-quality gold assets, including Tocantinzinho (TZ), Oko West, and Gurupi, with a combined M&I resource of 9.17 Moz and P&P reserves of 6.52 Moz as of March 2026.
Oko West is the largest gold project under construction globally, targeting 350 koz annual production and commercial production by January 2028.
Robust free cash flow from TZ supports internal funding for Oko West construction and exploration, with consolidated production expected to exceed 500 koz annually by 2028.
Construction at Oko West remains on schedule and on budget, with major infrastructure and equipment deliveries planned through 2027.
Exploration and resource expansion continue across all assets, with significant upside potential and ongoing drilling at depth and along strike.
Financial performance and outlook
Q1 2026 gold production reached 31,846 oz at an average grade of 1.03 g/t Au and 90.3% recovery, generating $56.2M in free cash flow.
2026 production guidance is 160–190 koz at total cash costs of $736–865/oz and AISC of $1,230–1,444/oz.
Consolidated free cash flow is projected to exceed $1.2B in 2028 at a $4,000/oz gold price, driven by ramp-up at Oko West.
Available liquidity stands at $638M, supporting ongoing capex and exploration programs.
2026 exploration budget is $42–50M, the largest in company history, with Oko West capex peaking at $514–568M.
Project milestones and operational highlights
TZ achieved commercial production in September 2024, with 2025 guidance of 171,871 oz at AISC of $1,155/oz and $255M mine-site free cash flow.
Oko West detailed engineering is 80% complete, with power plant and grinding mills scheduled for operation by mid-2027.
Gurupi advanced exploration continues, with updated resource and PEA expected in H2 2026.
Key construction milestones for Oko West include barge landing (Q2 2026), permanent kitchen (Q2 2026), and first gold in H2 2027.
Workforce at Oko West is 82% Guyanese, reflecting strong local engagement.
Latest events from G Mining Ventures
- Strong Q2 2026 results, record free cash flow, and major project progress amid higher cost guidance.GMIN
Q2 2026 - Transformational gold production growth to 700,000 oz by 2028, led by Tier-1 projects.GMIN
Corporate presentation - Significant construction progress and strategic acquisition drive project advancement and workforce unity.GMIN
Corporate presentation - On track for 500,000+ oz annual gold production by 2028, driven by flagship projects and exploration.GMIN
Corporate presentation - Construction milestones achieved with strong focus on safety, environment, and community.GMIN
Investor presentation - On track for 3x gold production growth by 2028, fully funded and expanding Tier-1 assets.GMIN
Corporate presentation - On track for 3x gold production growth by 2028, led by Oko West and Tocantinzinho.GMIN
Corporate presentation - Record Q3 gold output, strong cash flow, and Oko West construction drive multi-asset growth.GMIN
Q3 2025 - Record gold output, low costs, and major project milestones drive robust 2024 results and 2025 outlook.GMIN
Q4 2024