5 Aug, 2026Project development progress
Significant advancements in the industrial area, with major concrete works completed for CIP & CIL tanks, Pre-Leach Thickener, and SAG & Ball Mills; steel framing finished for the Assay Lab, Power Plant, and Mine Maintenance Facility.
CIL tank excavations are progressing, CIP tank foundations are complete, and installation is set for August; pipe rack structure work has started.
Pre-Leach Thickener construction is over halfway for exterior rings, with further pours scheduled for August.
SAG Mill foundation is finished with anchor bolts and plates installed; Ball Mill foundation concrete pour planned for August.
Primary Crusher mat foundation concrete pour is complete, with further structural work to continue in August.
Infrastructure and facilities
Mine Maintenance Facility has completed frame and slab pours for heavy truck, light truck, and warehouse; electrical and piping installation ongoing.
Assay Lab steel framing is complete, roof installation and interior electrical work to proceed in August; lab equipment procurement underway for September completion.
Power Plant has over 1,350 m³ of concrete poured, Engine Hall framing complete, and foundational work for day tank and stack finished; cable tray and electrical installation ongoing.
Tailings Storage Facility construction and access road are progressing on schedule, with detailed design and dam break analysis completed; site preparation for engineered fill is underway.
Strategic acquisitions and workforce initiatives
Acquisition of G2 Goldfields and the Oko-Ghanie project completed, consolidating adjacent deposits into a single operation.
Three new 44-seat coach buses have arrived to enhance employee transportation between key locations, improving comfort and efficiency.
Launched the "Proud To Be GMIN" campaign across Guyanese offices and the Oko site, strengthening workforce unity and company culture.
Employees celebrated Emancipation Day in Guyana by wearing traditional African attire, honoring heritage and resilience.
Latest events from G Mining Ventures
- On track for >500 koz gold production by 2028, fueled by Oko West and strong cash flow.GMIN
AGM 2026 presentation - Strong Q2 2026 results, record free cash flow, and major project progress amid higher cost guidance.GMIN
Q2 2026 - Transformational gold production growth to 700,000 oz by 2028, led by Tier-1 projects.GMIN
Corporate presentation - On track for 500,000+ oz annual gold production by 2028, driven by flagship projects and exploration.GMIN
Corporate presentation - Construction milestones achieved with strong focus on safety, environment, and community.GMIN
Investor presentation - On track for 3x gold production growth by 2028, fully funded and expanding Tier-1 assets.GMIN
Corporate presentation - On track for 3x gold production growth by 2028, led by Oko West and Tocantinzinho.GMIN
Corporate presentation - Record Q3 gold output, strong cash flow, and Oko West construction drive multi-asset growth.GMIN
Q3 2025 - Record gold output, low costs, and major project milestones drive robust 2024 results and 2025 outlook.GMIN
Q4 2024