G Mining Ventures (GMIN) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
16 Apr, 2026Project development progress
Approximately 2,300 m³ of concrete poured in March, advancing industrial area infrastructure.
Primary crusher excavation nearly complete, with deeper excavation and foundation pour next.
Power plant engine hall concrete works finished; fuel treatment house and day tank construction advancing.
Process plant foundations for CIP tanks, SAG Mill, and Ball Mill progressing, with over 1,000 m³ of concrete poured for Ball Mill.
Mine maintenance facility foundation completed; concrete slabs on grade in progress.
Equipment and fleet expansion
Komatsu PC4000 excavator active in mine pit, optimizing cost per ton with 22 m³ shovel capacity.
March saw delivery of 6 HD1500 trucks, a second PC4000, and commissioning of HM400 water truck and DR410 drill.
Mobile jaw crusher MOBICAT MC 110 EVO2 received and ready for deployment as aggregate plant.
Truck dumper body assembly ongoing, with three complete and fourth in progress; two 375 dozers commissioned, third arriving in April.
Site infrastructure and facilities
Emergency power generator commissioned, providing independent electricity; transmission lines to permanent camp completed, utilization set for April.
Temporary buildings constructed for material storage and truck shop, to be repurposed after construction.
Barge landing caisson near completion, enabling heavy material unloading by mid-April and supporting ongoing construction.
Dormitory expansion ongoing, with over 850 beds available and more being added; new camp kitchen and welcome centre progressing.
Latest events from G Mining Ventures
- Commercial production, strong cash flow, and major acquisitions drive growth and resource expansion.GMIN
Q4 202416 Apr 2026 - Production to exceed 500,000 oz by 2028, underpinned by Oko West and strong cash flow.GMIN
Corporate presentation16 Apr 2026 - Merger forms a top-tier Guyana gold hub with 500,000+ oz output and C$1B+ in synergies.GMIN
M&A announcement9 Apr 2026 - Record 2025 cash flow, net income, and major project milestones support robust growth outlook.GMIN
Q4 202526 Mar 2026 - Production to surpass 500,000 ounces annually by 2028, driven by rapid asset growth and execution.GMIN
2024 Precious Metals Summit Beaver Creek20 Jan 2026 - Gold output to triple by 2028, driven by low-cost mines and strong project pipeline.GMIN
Corporate presentation20 Jan 2026 - Record gold output and cash flow in Q2 2025 support self-funded growth and project advancement.GMIN
Q2 202523 Nov 2025 - Q1 2025 saw strong cash flow, low AISC, and major project advances, supporting 2025 growth.GMIN
Q1 202521 Nov 2025 - Record Q3 gold output, strong cash flow, and Oko West construction drive growth.GMIN
Q3 202513 Nov 2025