7 Jul, 2026Project development progress
Major advancements in mine maintenance facility, with warehouse framing complete and truck shop framing over 50% done.
Ball & SAG mills and thickener foundation construction progressing, with 5 of 7 CIP tank excavations complete.
SAG mill anchors embedded and ready for concrete pouring in early July.
Power plant structural framing finished, secondary slabs underway, and generators set for July delivery.
Fuel day tank foundations completed, preparing for installation of 9 tanks.
Safety and workforce
Over 1 million hours worked year-to-date with more than 1,400 employees and contractors.
Emphasis on safety through training, education, leadership interactions, and toolbox meetings.
Environmental and community initiatives
Recycling facility foundation completed, reinforcing commitment to waste management.
World Environment Day celebrated with a site-wide clean-up and biodiversity awareness campaign.
Participation in local STEM education events to promote mining careers and science education.
Latest events from G Mining Ventures
- On track for >500 koz gold production by 2028, fueled by Oko West and strong cash flow.GMIN
AGM 2026 presentation - Strong Q2 2026 results, record free cash flow, and major project progress amid higher cost guidance.GMIN
Q2 2026 - Transformational gold production growth to 700,000 oz by 2028, led by Tier-1 projects.GMIN
Corporate presentation - Significant construction progress and strategic acquisition drive project advancement and workforce unity.GMIN
Corporate presentation - On track for 500,000+ oz annual gold production by 2028, driven by flagship projects and exploration.GMIN
Corporate presentation - On track for 3x gold production growth by 2028, fully funded and expanding Tier-1 assets.GMIN
Corporate presentation - On track for 3x gold production growth by 2028, led by Oko West and Tocantinzinho.GMIN
Corporate presentation - Record Q3 gold output, strong cash flow, and Oko West construction drive multi-asset growth.GMIN
Q3 2025 - Record gold output, low costs, and major project milestones drive robust 2024 results and 2025 outlook.GMIN
Q4 2024