Project development progress

  • Major advancements in mine maintenance facility, with warehouse framing complete and truck shop framing over 50% done.

  • Ball & SAG mills and thickener foundation construction progressing, with 5 of 7 CIP tank excavations complete.

  • SAG mill anchors embedded and ready for concrete pouring in early July.

  • Power plant structural framing finished, secondary slabs underway, and generators set for July delivery.

  • Fuel day tank foundations completed, preparing for installation of 9 tanks.

Safety and workforce

  • Over 1 million hours worked year-to-date with more than 1,400 employees and contractors.

  • Emphasis on safety through training, education, leadership interactions, and toolbox meetings.

Environmental and community initiatives

  • Recycling facility foundation completed, reinforcing commitment to waste management.

  • World Environment Day celebrated with a site-wide clean-up and biodiversity awareness campaign.

  • Participation in local STEM education events to promote mining careers and science education.