20 Jan, 2026Business segment performance and outlook
Power segment secured capacity to deliver 70–80 heavy-duty gas turbines annually from 2026, up from 55, with strong global demand and higher pricing, especially for 2026–2027 slots.
Electrification is the fastest-growing segment, with backlog projected to triple from $6B to $18B by year-end and EBITDA margins expected to approach 9% in 2024, with further margin gains as higher-priced orders convert to revenue from 2026.
Onshore wind will deliver its fifth consecutive profitable quarter, achieving high single-digit EBITDA margins for the year, but offshore wind faces a $300M loss in Q3 due to project delays and cost accruals.
Offshore wind backlog reduced to $3B, with installation delays impacting profitability; full installation and commissioning have resumed, and profitability is now expected in Q4 2024.
Investor update scheduled for December 10 will address long-term targets, offshore wind progress, and capital allocation strategy.
Market trends and demand drivers
Gas power demand is rising globally, with significant orders from Saudi Arabia, Japan, Korea, Taiwan, and the U.S.; capacity expansion is primarily U.S.-based and funded by customer down payments.
Services revenue in gas is expected to grow by 50% later in the decade as customers invest more per outage to optimize assets for longer runtimes.
Electrification demand is shifting, with Europe as the largest market but North America as the fastest-growing, driven by grid and transformer needs; capacity expansion in North America will leverage existing facilities.
Pricing environments are favorable across gas and electrification, with margin accretion in backlog and continued ability to raise prices, including in North America.
Financial strategy and capital allocation
Strong cash position ($5.8B) expected to grow through Q3, Q4, and into 2025, with organic growth largely customer-funded via order progress and slot fees.
Capital allocation priorities include maintaining a strong balance sheet, returning capital to shareholders, and pursuing small, strategic M&A for growth adjacencies.
Cost reduction efforts are ongoing, with a target of $500M in G&A cost out over several years; further details to be shared at the December investor update.
Latest events from GE Vernova
- Backlog and margin growth, automation, and electrification drive robust outlook through 2028.GEV
Bank of America Global Industrials Conference 202618 Mar 2026 - Backlog and cash strength fuel growth in gas, electrification, and innovation for 2025 and beyond.GEV
Citi's Global Industrial Tech and Mobility Conference 20253 Feb 2026 - 2025 and 2028 targets raised, with strong growth, margin expansion, and robust shareholder returns.GEV
Investor Update3 Feb 2026 - Record $150.2B backlog, raised outlooks, and margin expansion signal strong future growth.GEV
Q4 20253 Feb 2026 - 2025 orders to hit $50B, electrification and gas power drive growth, wind remains challenging.GEV
Morgan Stanley’s 13th Annual Laguna Conference3 Feb 2026 - Q2 2024 saw margin expansion, strong cash flow, and upgraded guidance amid segment growth.GEV
Q2 20243 Feb 2026 - Double-digit growth and strong cash flow offset Offshore Wind losses, supporting 2024 outlook.GEV
Q3 202419 Jan 2026 - Record 2024 growth, margin expansion, and strong 2025 outlook led by Power and Electrification.GEV
Q4 202410 Jan 2026 - Robust growth in Gas and Grid, margin expansion, and buybacks drive a confident outlook.GEV
Barclays 42nd Annual Industrial Select Conference8 Jan 2026