Executive summary

  • Q1FY24 revenue was ₹1,124.22 crore, up 5% YoY; EBITDA was ₹161.5 crore, while continuing-operations PAT was a loss of ₹201.5 crore and consolidated loss after tax was ₹217.75 crore, including discontinued operations.

  • Letters of intent covered 75.69 lakh prepaid smart meters across 22 Uttar Pradesh districts under a 10-year project.

  • Board approval enabled fund-raising of up to ₹3,000 crore through QIP, FCCBs or other securities, subject to required approvals.

Financial highlights

  • Consolidated revenue from operations was ₹1,124.22 crore versus ₹1,068.68 crore in Q1FY23; total income was ₹1,190.42 crore.

  • EBITDA was ₹161.5 crore versus ₹145.6 crore YoY; margin was 15% versus 14%.

  • Consolidated loss after tax was ₹217.75 crore, including a ₹16.21 crore discontinued-operations loss; continuing-operations PAT was a ₹201.5 crore loss.

  • Consolidated results included an ₹85.44 crore impairment of GEL and underlying investments as an exceptional item.

  • Standalone revenue from operations was ₹257.64 crore; standalone loss was ₹26.32 crore after exceptional items, including a ₹51.19 crore exceptional charge.

Outlook and guidance

  • Priorities include higher utilization and efficiency at existing assets, open-capacity tie-ups through innovative PPAs, round-the-clock supply and operationalizing gas assets.

  • Growth priorities include power trading, asset-light technology offerings, C&I clean energy, hydro, electric mobility, storage and energy-efficiency services.

  • GKEL signed a five-year PPA to supply 102 MW round-the-clock to TANGEDCO and secured coal supply for the remaining 150 MW through the Shakti-III bid.

  • Krishnagiri SIR plans include ~210 acres with TIDCO; ~161 acres were under discussion for sale to a Tamil Nadu government agency in FY24.

  • Highway priorities include claims settlement, asset monetization, EPC order-book growth and bidding for railway-station PPP projects.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from GMR Power And Urban Infra