GMR Power And Urban Infra (GMRP&UI) Q4 23/24 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for GMR Power And Urban Infra Limited

Q4 23/24 earnings summary

20 Oct, 2026

Executive summary

  • Q4FY24 total income rose 11% YoY to INR 17.7bn and EBITDA reached INR 5.7bn; continuing-operations PAT was INR 1.7bn, including INR 3.331bn of acquisition-related exceptional income.

  • Energy-asset consolidation lifted reported income and EBITDA; Q4 PLFs were 80% at Warora and 85% at Kamalanga.

  • FY24 consolidated revenue from operations was ₹5,515.74 crore, up from ₹4,488.98 crore; EBITDA rose to ₹1,406.11 crore from ₹789.62 crore.

  • Auditors issued unmodified opinions while highlighting valuation, litigation and going-concern uncertainties at certain subsidiaries.

Financial highlights

  • FY24 consolidated total income was INR 48.3bn versus INR 58.8bn; EBITDA increased to INR 14.1bn from INR 7.9bn.

  • FY24 continuing-operations post-tax loss was ₹111.24 crore versus profit of ₹1,171.02 crore; exceptional items were ₹456 crore.

  • FY24 consolidated net loss including discontinued operations was ₹127.47 crore, versus net profit of ₹1,139.24 crore in FY23.

  • Standalone FY24 profit was ₹645.01 crore, including ₹682.04 crore of exceptional items; FY23 had a ₹282.86 crore loss.

  • Consolidated EBITDA margin was 33% in Q4FY24 versus 15% in Q4FY23; FY24 margin was 30% versus 14%.

Outlook and guidance

  • Smart-meter awards cover 75.69 lakh prepaid meters across 22 UP districts, worth ~INR 7,593 crore over 10 years; installation is scheduled over 27 months, followed by 93 months of operations.

  • Liquidity measures include asset monetization, infrastructure-claim recoveries, new financing, strategic investors, settlements and refinancing.

  • Management expects GWEL to generate profits and recover receivables through plant utilization, merchant sales and a replacement long-term PPA; GKEL contracted 102 MW of five-year round-the-clock supply to TANGEDCO.

  • Krishnagiri SIR plans include pursuing sale of ~318 acres to a Tamil Nadu government agency in FY25 and developing a further ~55 acres.

  • DFC packages 201 and 202 were ~98.27% and ~98.87% complete at 31 Mar 2024, with completion expected by September 2024.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from GMR Power And Urban Infra