GRP (BLU) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
30 Oct, 2026Executive summary
FY2024 continuing revenue fell 4.9% YoY to $17.97m; continuing net loss narrowed to $0.36m from $5.74m, aided by a non-recurring $4.75m gain on derecognising a PRC advance.
The Hose and Marine segment was classified as discontinued operations after a decision to sell it; the Perak affordable-housing project faced contractor disputes and delays.
Financial highlights
Revenue was $17.965m versus $18.895m in FY2023; continuing loss before tax was $58k versus $5.343m, and total loss after tax was $833k versus $6.361m.
Continuing operations recorded a $363k net loss; discontinued operations added a $470k loss.
Other operating income included a $4.747m non-recurring gain on derecognition of the PRC advance; a $2.130m ECL allowance and $1.626m provision for liquidated damages offset the improvement.
Cash and bank balances were $17.567m; total assets were $45.410m, liabilities $12.553m, and shareholders’ funds $33.900m at 30 June 2024.
Outlook and guidance
Priority is resolving the EESB dispute and containing delay impacts on the Perak affordable-housing project; execution of works resumed on 17 August 2024.
Plans include reprioritising to pursue new business opportunities and broaden the earnings base under new leadership.
No FY2024 dividend was proposed, citing weak market conditions and continued funding needs for the Malaysia housing project.
Latest events from GRP
- Revenue declined, but property work resumed with Phases 1 and 2 targeted for March 2026.BLU
AGM 2025 presentation - Revenue surged, losses narrowed, and affordable-housing projects progressed toward completion.BLU
AGM 2026 presentation - Revenue grew 23%, but lower gross profit and a wider pretax loss kept results under pressure.BLU
Q3 2024 - Losses narrowed, but a contractor dispute delayed the affordable housing project.BLU
AGM 2024 presentation - Metrology growth and stronger cash offset property delays and a quarterly net loss.BLU
Q1 2025 - Profit returned as metrology gains offset property weakness and project delays.BLU
H1 2025 - Perak project charges drove deeper losses, offset partly by metrology growth and $19.56m cash.BLU
Q3 2026 - Project delays and cost revisions drove a $8.79m FY2025 loss; housing completion targets extend to 2026.BLU
H2 2025 - Revenue grew 11.6%, but pretax profit dropped to S$62k amid housing project costs.BLU
H1 2026