Hallador Energy Company (HNRG) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Hallador Energy Company

Investor presentation summary

11 Nov, 2026

Platform and operating profile

  • Vertically integrated independent power producer serving MISO, with 1 GW Merom generation capacity and 100% ownership of its interconnection.

  • Sunrise Coal’s anticipated annualized production pace is ~3.7 million tons, supporting Merom fuel needs and third-party coal sales.

  • TTM revenue was ~$439M and TTM Adjusted EBITDA was ~$28M as of September 30, 2026.

  • Forward contracted sales totaled ~$3.0B, including ~$0.5B of intercompany coal sales eliminated in consolidation.

Contracted revenue and pricing

  • Three multi-year PPAs executed in 2026 added ~$1.4B of contracted capacity revenue through mid-2040, with ~14 years sold forward.

  • ~95% of accredited capacity is under contract through 2035; accredited capacity and energy revenue reaches $73/MWh in 2030 and $75/MWh for 2031–2035.

  • The October 2026 PPA is priced above the May agreement at $80+/MWh for 2029–2035 periods; contracted energy agreement revenue is expected to be $422M.

  • Retained open energy positions preserve exposure to MISO market pricing, while owned fuel controls ~90% of variable cost.

Turtle Creek gas expansion

  • Turtle Creek is a ~460 MW natural gas project at Merom, estimated at ~$800M or ~$1,700/kW, with commercial operation targeted for 2H 2028.

  • MISO completed the interconnection study; the project’s targeted ~3-year timeline compares with 7+ years for greenfield development.

  • Up to $675M of debt financing was secured, including a $600M construction bridge facility with $550M funded and $50M delayed draw, plus an expected $75M revolver.

  • Final investment decision is targeted before year-end 2026, subject to Board approval; engineering and construction agreement negotiations were in final stages as of November 9, 2026.

  • $53M had been invested in Turtle Creek as of September 30, 2026; majority of project financing was secured.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.