11 Nov, 2026Platform and operating profile
Vertically integrated independent power producer serving MISO, with 1 GW Merom generation capacity and 100% ownership of its interconnection.
Sunrise Coal’s anticipated annualized production pace is ~3.7 million tons, supporting Merom fuel needs and third-party coal sales.
TTM revenue was ~$439M and TTM Adjusted EBITDA was ~$28M as of September 30, 2026.
Forward contracted sales totaled ~$3.0B, including ~$0.5B of intercompany coal sales eliminated in consolidation.
Contracted revenue and pricing
Three multi-year PPAs executed in 2026 added ~$1.4B of contracted capacity revenue through mid-2040, with ~14 years sold forward.
~95% of accredited capacity is under contract through 2035; accredited capacity and energy revenue reaches $73/MWh in 2030 and $75/MWh for 2031–2035.
The October 2026 PPA is priced above the May agreement at $80+/MWh for 2029–2035 periods; contracted energy agreement revenue is expected to be $422M.
Retained open energy positions preserve exposure to MISO market pricing, while owned fuel controls ~90% of variable cost.
Turtle Creek gas expansion
Turtle Creek is a ~460 MW natural gas project at Merom, estimated at ~$800M or ~$1,700/kW, with commercial operation targeted for 2H 2028.
MISO completed the interconnection study; the project’s targeted ~3-year timeline compares with 7+ years for greenfield development.
Up to $675M of debt financing was secured, including a $600M construction bridge facility with $550M funded and $50M delayed draw, plus an expected $75M revolver.
Final investment decision is targeted before year-end 2026, subject to Board approval; engineering and construction agreement negotiations were in final stages as of November 9, 2026.
$53M had been invested in Turtle Creek as of September 30, 2026; majority of project financing was secured.
Latest events from Hallador Energy Company
- Merom rebounded as Turtle Creek advanced, with financing and execution risks remaining.HNRG
Q3 2026 - Secured $2.4B in forward sales and expanding capacity 40% with a new natural gas project.HNRG
Investor presentation - Q2 2026 net loss driven by higher costs, but $2.4B in forward sales boosts revenue outlook.HNRG
Q2 2026 - $350M Siemens turbine deal accelerates multi-fuel growth and targets revenue by 2029.HNRG
M&A announcement - 12-year, $1B+ capacity deal nearly doubles forward sales and boosts liquidity despite Q1 loss.HNRG
Q1 2026 - Annual meeting to vote on directors, executive pay, and auditor, with focus on governance and performance.HNRG
Proxy filing - Election of directors, executive pay approval, and auditor ratification headline the 2026 meeting.HNRG
Proxy filing - Expanding capacity by 50% amid surging demand and robust contracted sales in a high-risk region.HNRG
Investor presentation - Q3 2025 saw 40% revenue growth, $23.9M net income, and a 525MW gas expansion filed.HNRG
Q3 2025