13 Nov, 2026

Strategic ambition and portfolio

  • Long-term ambition: exceed 500koz of annual gold production by 2030; presentation production scenarios show a 300koz target by 2030, with growth dependent on projects and potential additions.

  • Portfolio spans operating mines La Colorada and San Agustin, development projects Ana Paula and Cerro del Gallo, and pipeline assets including Goldstrike, San Antonio and Unga.

  • Portfolio totals 1.939Moz of probable gold reserves, 7.240Moz of measured and indicated resources, and 1.426Moz of inferred resources.

Operating mines and 2026 guidance

  • Consolidated 2026 guidance: 50–55koz gold, 290–320koz silver, cash cost of $1,850–1,950/oz Au and AISC of $2,025–2,125/oz Au.

  • Q2 2026 production was 14,803oz; YTD cash costs were $1,630/oz and AISC $2,155/oz, with mine operating earnings of $21.0M after tax.

  • La Colorada 2026 gold guidance is 20,000–22,300oz; injection leaching supports production through 2026–27, while Veta Madre ore production is planned from H1 2027.

  • San Agustin 2026 gold guidance is 30,000–32,700oz; a 25,000–30,000m oxide drilling program is targeting mine-life extension, including a 12-month extension target.

Ana Paula development

  • PEA outlines a 9-year mine life, 874,700oz of gold produced and 101koz annual production after ramp-up; LOM average AISC is $1,011/oz.

  • At a $2,400/oz base-case gold price, PEA after-tax NPV is $426M and IRR 28.1%; at $3,800/oz, after-tax NPV is $1,012M and IRR 51.3%.

  • Feasibility Study work is underway, with completion targeted for Q2 2027; a mid-2027 construction decision and first gold before end-2028 are targeted.

  • Proposed FS work includes initial throughput of 2,000tpd, potential mid-mine-life expansion to 2,500tpd, underground crushing and lower cut-off grades.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Heliostar Metals