Heliostar Metals (HSTR) Precious Metals & Critical Minerals Virtual Investor Conference summary

Event summary combining transcript, slides, and related documents.

Logotype for Heliostar Metals Ltd

Precious Metals & Critical Minerals Virtual Investor Conference summary

14 Oct, 2026

Growth strategy and production

  • FY production guidance: 50,000–55,000 oz, versus 33,000 oz last year; two producing mines are expected to generate ~$150 million for Ana Paula development.

  • Long-term target is 300,000–500,000 oz of annual production; Ana Paula is targeted to add 100,000 oz/year in 2028, followed by Cerro del Gallo before end-2030.

  • Mexican portfolio acquired for $15 million cash and owned 100%; assets have generated >$70 million in operating cash flow since acquisition.

  • June 30 cash was $43 million with zero debt; plan pairs ~$150 million of operating cash flow with ~$200 million of project debt for Ana Paula.

  • At gold prices above $3,800/oz, Ana Paula is expected to be funded without equity; a bolt-on growth opportunity could require an equity issuance.

Ana Paula development

  • November 2025 PEA outlines an underground mine processing 1,800 t/day, producing 100,000 oz/year at $1,000/oz AISC.

  • Feasibility study is on track for Q2 next year; 25,000 m of drilling upgraded inferred material, supporting a target of 10 years at 100,000 oz/year.

  • Optimization work includes a 2,000 t/day plant, front-end equipment sized for 2,500 t/day, and dual declines to reduce haulage and ventilation costs.

  • Underground permit application was submitted; the underground footprint is ~65% smaller than the previously permitted open-pit plan, with a 6–8 month government review expected.

  • Construction decision is targeted for Q2 next year; $15 million is planned for long-lead equipment in Q4, construction is expected to take 18 months, and first gold is targeted before end-2028.

Producing mines and cash generation

  • La Colorada residual leaching is producing ~1,000 oz/month; fresh Veta Madre ore is expected in Q2 next year, with production through 2027–2028 before a Creston pit cutback adds four years of mine life.

  • San Agustin reached steady-state production; the initial 14-month mine plan is expected to generate >$70 million of net free cash flow through Q2 next year.

  • Drilled extensions at San Agustin could add 6–9 months of mine life through 2027–2028 and ~$40 million of net free cash flow.

  • Q2 production was described as repeatable over the next several quarters, supported by a full quarter at San Agustin and La Colorada residual leaching.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Heliostar Metals