Dariba development

  • Established in 1983, the complex includes Dariba Smelting Complex (DSC), RD Mine and Sindesar Khurd (SK) Mine.

  • SK Mine was commissioned in 2006 and DSC in 2010.

  • Early site constraints included inadequate water and electricity, barren land, poor infrastructure and connectivity, and a lack of skilled manpower.

Current operations and scale

  • DSC benefits from nearby lead-zinc mines at SK and Rajpura Dariba, supporting complex self-sufficiency.

  • SK and RD are described as among India's leading underground mines, with a focus on cost efficiency.

  • Ore production is 7 MnT annually; resources and reserves are ~190 MnT post depletion.

  • SK is the world's second-largest silver-producing mine and is described as one of the most digitally advanced mines globally.

  • Smelting capacity is 240 KTPA for zinc and 120 KTPA for lead.