Hindustan Zinc (500188) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
5 Oct, 2026Market position and asset base
World's largest integrated zinc producer, among the top five silver producers globally, and holds 77% of India's primary zinc market.
Total resources and reserves of 453.2 Mnt, including 189.1 Mnt of ore reserves and 13.1 Mnt of contained metal reserves; mine life exceeds 25 years.
FY2025 production reached 1,095 kt mined metal, up 1%, 1,052 kt refined metal, up 2%, and 687 tonnes of silver.
Zinc cost of production was US$1,052/tonne, the lowest in four years; value-added products reached 179 kt, or ~22% of sales.
FY2025 financial and shareholder performance
Revenue rose 18% YoY to 34,083 crore; EBITDA increased 28% to 17,465 crore and PAT grew 33% to 10,353 crore.
Free cash flow from operations was 10,857 crore, supporting growth capex, debt reduction and shareholder distributions.
Total shareholder returns were ~68%; dividend distribution totaled 12,253 crore, with a 29 per-share dividend.
EBITDA margin was 51% in FY2025, versus 47% in FY2024; return on capital employed reached 58%, versus 42%.
Expansion and strategic priorities
Phase 1 capex of 16,000 crore approved, including a 250 ktpa smelter at Debari and a 10 Mtpa tailings reprocessing plant costing 3,823 crore.
Post-expansion capacity targets are 1,379 ktpa refined metal and 1,510 ktpa mined metal; FY2030 targets include 40 Mnt metal resources and reserves.
FY2030 plans target 2 Mtpa underground mining and smelting capacity, 1,500 tonnes of silver, and value-added products at 50% of the portfolio.
Zinc cost target is US$1,000/tonne in FY2027 and below US$1,000/tonne by FY2030, alongside renewable energy shares of 55% and 70%, respectively.
Latest events from Hindustan Zinc
- Record FY25 results support a 2-million-ton, multi-metal expansion agenda.500188
AGM 2025 - Record output and lower costs offset weaker prices, with FY2025 guidance targeting further growth.500188
AGM 2024 - A 456.3 Mt resource base underpins production growth and a renewable-powered transition.500188
Investor presentation - A long-life, low-cost zinc base backs capacity growth and renewable power expansion.500188
Investor presentation - Dariba combines 7 MnT annual ore production with 360 KTPA of zinc and lead smelting capacity.500188
Investor presentation - A 25+ year resource base underpins growth in zinc, silver and renewable power.500188
Investor presentation - Market leadership and low costs underpin expansion in metals, silver and critical minerals.500188
Investor presentation - A 250 ktpa expansion launches a 2x growth strategy backed by strong production and market leadership.500188
Investor presentation - Low-cost zinc leadership meets capacity expansion and ambitious sustainability goals.500188
Investor presentation