i-80 Gold (IAU) Q1 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2025 earnings summary
28 Nov, 2025Executive summary
Filed technical studies and Preliminary Economic Assessments (PEAs) for all five gold projects, supporting a staged development plan targeting 500,000 ounces of annual gold production by the early 2030s, with a combined after-tax NPV of $1.6B at $2,175/oz gold and $4.5B at $2,900/oz gold.
Q1 2025 revenue increased to $14.0M from $8.4M year-over-year, driven by higher gold sales and prices at Granite Creek, with gold sales totaling approximately 5,000 ounces.
Net loss widened to $41.2M ($0.10/share), mainly due to non-cash revaluation losses on gold prepay and silver purchase agreements, impacted by higher forward gold prices.
Liquidity improved to $25M pro forma after securing a $12M working capital facility with Auramet, supporting ongoing development and permitting activities.
Welcomed new COO Paul Chawrun and acknowledged outgoing COO Matt Gili.
Financial highlights
Gold sales for Q1 2025 totaled 4,952–5,000 ounces at an average realized price of $2,825/oz, up from 4,061 ounces at $2,063/oz year-over-year.
Total revenue was $14M, with a gross loss of $10.8M and operating loss of $15.8M for the quarter.
Cash used in operations was $22.7M, with a quarter-end cash balance of $13.5M, increasing to $25M pro forma with new financing.
Loss per share was $(0.10), compared to $(0.06) year-over-year.
Outlook and guidance
Targeting production ramp-up to 500,000 ounces annually by early 2030s, with company-wide gold extraction expected between 30,000 and 40,000 ounces in 2025.
Granite Creek Underground projected to contribute 20,000–30,000 ounces in 2025, with steady-state output expected in H2 2025; Ruby Hill and Lone Tree heap leach operations to add about 10,000 ounces.
Growth expenditures for 2025 expected to range between $40M and $50M, focused on permitting, feasibility studies, and advancing Archimedes Underground.
Feasibility studies for Cove and Lone Tree expected in 2025; permitting for Cove anticipated by end of 2027.
Latest events from i-80 Gold
- Three-phase Nevada mining plan targets 600,000+ oz gold output and major value growth.IAU
35th BMO Global Metals, Mining & Critical Minerals Conference24 Feb 2026 - Gold output and revenue surged in 2025, with major financing fueling accelerated project growth.IAU
Q4 202523 Feb 2026 - Q2 net loss was $36.8M on $7.2M revenue as project development and gold sales advanced.IAU
Q2 20241 Feb 2026 - Q3 net loss was $38.1M on $11.5M revenue, with recapitalization and project studies ongoing.IAU
Q3 202414 Jan 2026 - Development plan targets 500,000 oz gold by 2030s; recapitalization and new financing in progress.IAU
Q4 202426 Dec 2025 - Refurbishment enables in-house gold processing, higher margins, and first gold by late 2027.IAU
Study Update19 Dec 2025 - Advancing five Nevada gold projects to feasibility, targeting 400,000+ oz/year by 2031.IAU
Investor Day 20252 Dec 2025 - Revenue and gold sales surged in Q2 2025, fueling project growth and recapitalization.IAU
Q2 202523 Nov 2025 - Gold sales and revenue surged, gross profit turned positive, and key Nevada projects advanced.IAU
Q3 202515 Nov 2025