Iluka Resources (ILU) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
2 Nov, 2026Construction and commissioning
Construction 65% complete at 30 September 2026; capital expenditure $1,237m against a total capital estimate of $1.7–1.8bn. All major equipment delivered and engineering 100% complete.
SMPEI works advancing, with pipe racks, large tanks and main SX circuit buildings progressing; commissioning of completed packages underway and switchrooms energized.
Construction completion and a two-year ramp-up are planned; commissioning priorities include operator training, stable processes and mineral commissioning with Eneabba feedstock.
Refinery design and capacity
Designed for flexible feed sources and rare earth oxide output; the process uses conventional sulfuric cracking, leaching and nitrate-based separation.
Nameplate concentrate capacity is 55ktpa; total rare earth oxide capacity is 23,000tpa, including 5,500tpa NdPr oxide and 750tpa DyTb oxide.
Light rare earth circuit capacity is 17ktpa, with short-term capacities fixed; additional separation capacity, including for yttrium oxide, could be considered post-commissioning.
Design features include progressive neutralisation for purification, seven main separation stages and permanent, lined waste storage in an ex-mine void.
Feedstock and production options
Supply sources include the Eneabba stockpile, Balranald and third-party projects including Lindian Resources’ Kangankunde, VHM’s Goschen and Northern Minerals’ Browns Range.
Illustrative blends range from a light rare earth focus using Eneabba and Balranald to a heavy rare earth focus incorporating Wimmera, Northern Minerals and VHM feedstocks.
Illustrative outputs span 3,600–4,300tpa NdPr, ~180–1,000tpa DyTb and 350–5,000tpa HRE plus yttrium contained in carbonate, depending on feed blend.
Latest events from Iluka Resources
- Q3 zircon pricing strengthened as Balranald ramp-up and Eneabba construction progressed.ILU
Q3 2026 TU - Cash flow surged and debt fell as key projects advanced, despite lower H1 revenue.ILU
H1 2026 - Lower H1 2026 production offset by strong cash flow and rare earths milestones.ILU
Q2 2026 TU - AGM confirmed strategic progress on rare earths, disciplined finances, and board transitions.ILU
AGM 2025 - Integrated rare earths refinery set for 2027, fully funded and backed by long-term supply deals.ILU
Investor presentation - Revenue and profit fell, but cost cuts and rare earths progress support the 2026 outlook.ILU
H2 2025 - Net profit dropped 31% as revenue and prices fell, but key projects and cost controls advanced.ILU
H1 2025 - Revenue and profit fell, but stable pricing and project progress support future growth.ILU
H1 2024 - Revenue and profit fell, but margins held and major projects are fully funded.ILU
H2 2024