IREN (IREN) Q1 2027 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 earnings summary
5 Nov, 2026Executive summary
Revenue rose 66% QoQ to $228M, led by AI Cloud revenue of $200M; net loss was $263M.
Operating ARR reached $1B; revenue backlog was $20.3B, up 22% QoQ, with approximately two-thirds tied to investment-grade counterparties.
More than $4B of contracted, fully funded ARR is targeted to be operational by January 2027, potentially extending to end-February.
Vertically integrated AI Cloud, data center, and land-and-power operations support demand-led investment, while expansion depends on delivery, customer acceptance, and financing.
Financial highlights
Revenue was $228M, including $200M from AI Cloud and $28M from Bitcoin mining; total segment gross profit was $182M, including $172M from AI Cloud.
Adjusted EBITDA was $66M versus $19M QoQ; net loss was $263M versus $684M, including $148M of depreciation and amortization and $106M of stock-based compensation.
SG&A was $217M, including $106M of stock-based compensation; depreciation and amortization was $148M.
Operating cash inflow was $529M; investing cash outflow was $5.146B, driven by AI hardware and data center investment.
Outlook and guidance
More than $4B of ARR is targeted to be operational by January 31, 2027, potentially extending to end-February; commissioning, testing, and customer acceptance affect revenue timing.
Remaining planned FY27 CapEx was $15B, including $6B still to fund; approximately $9B of cash, committed GPU financing, and prepayments plus targeted financing and other sources are expected to cover it, subject to market conditions.
Targeting 0.8GW of data center capacity by end-2027, with the initial 0.3GW program in final stages; further expansion may require additional CapEx.
The Bitcoin mining transition is targeted to be substantially complete by December 31, 2026; immaterial mining operations are expected to continue through CY2027.
Certain AI Cloud capacity previously targeted for delivery by December 31, 2026 is now expected in the following quarter due to customer design changes, supply timing, and third-party delays.
Latest events from IREN
- AGM seeks six approvals as AI infrastructure expansion and long-term executive incentives advance.IREN
Proxy filing - AGM agenda pairs two share repurchase approvals with director, pay and auditor votes.IREN
Proxy filing - AI Cloud revenue surged 8x, $4bn ARR contracted, $19bn funding, and FY26 net loss from impairments.IREN
Q4 2026 - Founder-CEOs granted major equity awards to secure long-term leadership amid rapid global growth.IREN
Proxy filing - AI Cloud pivot accelerates with $3.4B NVIDIA deal and $3.1B ARR contracted amid global expansion.IREN
Q3 2026 - $3.6B GPU financing secured, AI Cloud ramps, $3.4B ARR targeted for 2026 amid Q2 net loss.IREN
Q2 2026 - Accelerated expansion to 50 exahash, low costs, and AI growth amid lower mining revenue.IREN
Q1 2025 - Record Adjusted EBITDA and revenue, with fully funded expansion to 30 EH/s and 510MW.IREN
Q4 2024 - Record Q2 profit, surging mining revenue, and major AI/data center expansion underway.IREN
Q2 2025