IREN (IREN) Q4 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 earnings summary
27 Aug, 2026Executive summary
$4 billion of ARR contracted for FY26 capacity, with $1 billion currently operating and the remainder expected by year-end; 2026 capacity is nearly sold out and customer base expanded with new multi-cloud contracts and renewals from major AI developers, hyperscalers, and enterprises.
Transitioned from Bitcoin mining to AI Cloud Services, with significant investments in data center expansion, GPU infrastructure, and acquisitions of Mirantis and Nostrum to strengthen software and expand into Europe.
Raised $19 billion in the past 12 months to fund growth, including $6.5 billion in GPU financing in the last 3 months.
Delivered Horizon 1 (50MW IT) to Microsoft, with three more 50MW deployments targeted for the December quarter.
Substantial growth in headcount and organizational capability, including five new C-suite appointments, to support rapid expansion.
Financial highlights
FY26 total revenue was $707.0 million, up from $501.0 million in FY25; AI Cloud Services revenue grew nearly 8x to $128.8 million from $16.4 million year-over-year.
Net loss for FY26 was $(702.6) million, impacted by $638.8 million in non-cash impairments and transition costs.
Adjusted EBITDA for FY26 was $245.7 million (35% margin), down from $269.7 million (54% margin) in FY25.
Q4 FY26 revenue: $137.2 million (down from $144.8 million in Q3 FY26); net loss $(684.0) million, impacted by $450.4 million in asset impairments.
Cash and cash equivalents at year-end were $7.6 billion, up from $564.5 million in FY25.
Outlook and guidance
FY27 CapEx guidance of $25–$30 billion, covering contracted deployments, new builds, and early-stage investments for 2028 and beyond.
Existing cash and committed GPU financing/prepayments of $14 billion; targeting an additional $8 billion in GPU financing/prepayments.
2026 capacity is nearly sold out; late-stage discussions for 2027 and 2028 capacity are ongoing.
Contracted pricing is increasing, with recent 3-year contracts exceeding $20 million revenue per MW and active discussions at $25 million per MW.
Global expansion targets over 5 GW data center pipeline, with 0.3 GW IT delivery in 2026 and 0.8 GW in 2027.
Latest events from IREN
- Founder-CEOs granted major equity awards to secure long-term leadership amid rapid global growth.IREN
Proxy filing - AI Cloud pivot accelerates with $3.4B NVIDIA deal and $3.1B ARR contracted amid global expansion.IREN
Q3 2026 - $3.6B GPU financing secured, AI Cloud ramps, $3.4B ARR targeted for 2026 amid Q2 net loss.IREN
Q2 2026 - Shareholders will vote on major governance, compensation, and share repurchase proposals.IREN
Proxy Filing - Shareholders will vote on key governance, compensation, and share repurchase proposals after a record year.IREN
Proxy Filing - Shareholders to vote on governance changes, executive pay, and share repurchase proposals.IREN
Proxy Filing - Accelerated expansion to 50 exahash, low costs, and AI growth amid lower mining revenue.IREN
Q1 2025 - Record Adjusted EBITDA and revenue, with fully funded expansion to 30 EH/s and 510MW.IREN
Q4 2024 - Record Q2 profit, surging mining revenue, and major AI/data center expansion underway.IREN
Q2 2025