June 2025 Thacker Pass Site Tour Presentation
Logotype for Lithium Americas Corp

Lithium Americas (LAC) June 2025 Thacker Pass Site Tour Presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Lithium Americas Corp

June 2025 Thacker Pass Site Tour Presentation summary

14 Sep, 2025

Project overview and investment highlights

  • Thacker Pass Phase 1 is fully permitted, funded, and under construction, targeting completion in late 2027 with a nominal production capacity of 40,000 t/y battery-quality lithium carbonate and expansion potential to 160,000 t/y over five phases and an 85-year mine life.

  • The project is a joint venture: 62% owned by the company and 38% by General Motors, with GM holding offtake rights for up to 100% of Phase 1 and 38% of Phase 2 for 20 years.

  • Funding includes a $2.26 billion U.S. DOE loan at the Treasury rate, $945 million from GM, and $250 million from Orion Resource Partners, with additional non-binding proposals for Phase 2 financing.

  • Thacker Pass is the world’s largest known measured lithium resource and reserve, with a top-tier leadership team experienced in large-scale project development.

  • The project is strategically located in Nevada, with access to highways, rail, water rights, and a dedicated workforce hub.

Project execution and construction progress

  • Approximately 60% of detailed engineering is complete, with all long-lead equipment awarded and first permanent concrete placed in May 2025.

  • The workforce hub in Winnemucca will provide housing for up to 1,997 workers, with first occupancy expected in the second half of 2025.

  • Major construction milestones include early works, infrastructure, and process plant pad completion, with mechanical completion and initial production targeted for late 2027.

  • The project is de-risked through advanced procurement, detailed engineering, and a proven technical flowsheet validated at the Lithium Technical Development Center.

  • Collaboration with leading contractors such as Bechtel and Sawtooth Mining ensures expertise in design, construction, and reclamation.

Technical process and sustainability

  • The process uses standard, proven equipment for beneficiation, hydrometallurgy, and lithium carbonate production, with no novel technology required.

  • Onsite sulfuric acid production provides 40% of the plant’s power needs, with the remainder from hydroelectric sources.

  • Water is recycled an average of seven times, and a zero liquid discharge system eliminates process water release to the environment.

  • All waste is stored in a double-lined dry stack facility, reclaimed concurrently with mining to minimize environmental impact.

  • The project has achieved ISO 9001:2015 certification and implements a comprehensive ESG and safety program, including community agreements and local hiring.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more