Lithium Americas (LAC) June 2025 Thacker Pass Site Tour Presentation summary
Event summary combining transcript, slides, and related documents.
June 2025 Thacker Pass Site Tour Presentation summary
14 Sep, 2025Project overview and investment highlights
Thacker Pass Phase 1 is fully permitted, funded, and under construction, targeting completion in late 2027 with a nominal production capacity of 40,000 t/y battery-quality lithium carbonate and expansion potential to 160,000 t/y over five phases and an 85-year mine life.
The project is a joint venture: 62% owned by the company and 38% by General Motors, with GM holding offtake rights for up to 100% of Phase 1 and 38% of Phase 2 for 20 years.
Funding includes a $2.26 billion U.S. DOE loan at the Treasury rate, $945 million from GM, and $250 million from Orion Resource Partners, with additional non-binding proposals for Phase 2 financing.
Thacker Pass is the world’s largest known measured lithium resource and reserve, with a top-tier leadership team experienced in large-scale project development.
The project is strategically located in Nevada, with access to highways, rail, water rights, and a dedicated workforce hub.
Project execution and construction progress
Approximately 60% of detailed engineering is complete, with all long-lead equipment awarded and first permanent concrete placed in May 2025.
The workforce hub in Winnemucca will provide housing for up to 1,997 workers, with first occupancy expected in the second half of 2025.
Major construction milestones include early works, infrastructure, and process plant pad completion, with mechanical completion and initial production targeted for late 2027.
The project is de-risked through advanced procurement, detailed engineering, and a proven technical flowsheet validated at the Lithium Technical Development Center.
Collaboration with leading contractors such as Bechtel and Sawtooth Mining ensures expertise in design, construction, and reclamation.
Technical process and sustainability
The process uses standard, proven equipment for beneficiation, hydrometallurgy, and lithium carbonate production, with no novel technology required.
Onsite sulfuric acid production provides 40% of the plant’s power needs, with the remainder from hydroelectric sources.
Water is recycled an average of seven times, and a zero liquid discharge system eliminates process water release to the environment.
All waste is stored in a double-lined dry stack facility, reclaimed concurrently with mining to minimize environmental impact.
The project has achieved ISO 9001:2015 certification and implements a comprehensive ESG and safety program, including community agreements and local hiring.
Latest events from Lithium Americas
- Thacker Pass, the largest U.S. lithium project, is fully funded and on track for 2027 completion.LAC
Gabelli Funds' 16th Annual Specialty Chemicals Symposium2 Dec 2025 - Thacker Pass construction accelerates with major financing, but net loss rises on non-cash items.LAC
Q3 202513 Nov 2025 - Thacker Pass advances as the largest U.S. lithium project, fully funded and under major construction.LAC
Corporate Presentation14 Sep 2025 - Thacker Pass construction advances, with strong cash, key investments, and 2027 completion targeted.LAC
Q2 202526 Aug 2025 - Thacker Pass Phase 1 fully funded and advancing toward late 2027 production.LAC
Q4 202416 Jun 2025 - $2.26B DOE loan and $625M GM JV propel Thacker Pass toward major construction.LAC
Q3 202413 Jun 2025 - Thacker Pass secures major funding and partnerships, targeting U.S. lithium production by 2027.LAC
Corporate Presentation13 Jun 2025 - Thacker Pass construction fully funded for 2H24 start, with cash reserves and key loans secured.LAC
Q2 202413 Jun 2025 - Thacker Pass is set to become a leading U.S. lithium supplier, backed by GM and DOE support.LAC
Corporate Presentation13 Jun 2025