Maire (MAIRE) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
30 Oct, 2026Business model and positioning
Nextchem sells proprietary low-carbon and circular technologies in 12–18-month cycles; Tecnimont delivers integrated E&C services on 3–4-year cycles, providing complementary growth and revenue visibility.
The integrated model spans feasibility through commissioning, with MET Development supporting selected equity initiatives, financing, permits, grants and industrial partnerships.
The asset-light, people-driven model combines broad process-design capabilities, complex-project experience and AI-enabled operational improvement.
Markets and technology portfolio
Installed energy capacity is projected to rise from 10.2 TW in 2024 to ~20 TW in 2035; the strategy emphasizes a pragmatic multi-source energy mix shaped by regional needs.
At 30 Sep 2026, Nextchem had 80+ market-ready technologies, 50+ proprietary solutions, ~1,200 employees and €786m backlog.
Growth platforms span fertilizers, low-carbon fuels, recycling, critical materials and nuclear; Ballestra expanded fertilizer and inorganic chemistry offerings, while ETEK added precious-metals recovery.
The MEAB acquisition was announced for €8.0m consideration, with closing expected in Q4 2026; its separation and purification technologies broaden critical-materials capabilities.
9M 2026 performance and execution
Group revenue was €5,636.7m, up 7.7% YoY; EBITDA was €414.3m, up 15.7%, with a 7.4% margin; net income was €243.0m, up 18.6%.
Nextchem revenue reached €476.3m, up 54.0% YoY, and EBITDA €113.2m, up 41.0%; Tecnimont revenue was €5,160.4m, up 4.8%, and EBITDA €301.1m, up 8.4%.
Group backlog reached €16.4bn at 30 Sep 2026, including €265m from Ballestra; 9M book-to-bill was 1.6x, backlog cover 2.2x and sustainability-related order intake exceeded 13%.
Major awards included a $4.3bn UAE rich-gas EPC project, a $2.3bn Saudi water-injection EPC project and a €1.3bn integrated fertilizer project in Argentina.
Hail and Ghasha construction was ~80% complete at 30 Sep 2026; alternative routing and ~2,800 container deliveries supported execution amid reduced Strait of Hormuz operability.
Latest events from Maire
- FY23 growth and a €15.0bn backlog support a plan for >€10bn revenue by 2033.MAIRE
H2 2023 & CMD 2024 - 9M EBITDA rose 15.7% as €8.9bn of orders lifted backlog to €16.4bn.MAIRE
Q3 2026 - Ambitious 2035 plan targets €13bn+ revenue, 11% margins, and 60% sustainability-related sales.MAIRE
Corporate presentation - H1 2026 saw strong growth, record backlog, and guidance confirmed amid major acquisitions.MAIRE
Q2 2026 - Q1 2026 saw 7.6% revenue growth, 19.9% net income rise, and record €15.7bn backlog.MAIRE
Q1 2026 - Revenues and EBITDA surged, net income rose 41.8%, and backlog hit €13.9 billion.MAIRE
Q3 2025 - Double-digit growth, margin expansion, and record backlog support 2024 guidance.MAIRE
Q3 2024 - Q1 2025 saw 35% revenue growth, record backlog, and confirmed guidance amid robust order intake.MAIRE
Q1 2025 - Record 2024 growth and strong outlook driven by sustainability, tech, and robust backlog.MAIRE
H2 2024 & CMD 2025