Maronan Metals (MMA) Investor Presentation summary
Event summary combining transcript, slides, and related documents.
Investor Presentation summary
14 Oct, 2025Project overview and resources
Advancing a large, undeveloped silver-lead and copper-gold resource in a Tier 1 mining jurisdiction with strong infrastructure and flexible development options.
Global resources: 122 Moz silver, 2 Mt lead, 271kt copper, 0.76 Moz gold; 100% owned, royalty free.
Silver-lead resource: 33.1 Mt @ 108 g/t Ag, 6.0% Pb; copper-gold resource: 32.0 Mt @ 0.85% Cu, 0.63 g/t Au.
Starter zone resources: 12.2 Mt silver-lead, 7.0 Mt copper-gold, both open at depth and with growth potential.
Only a small portion of global resources included in the current economic assessment, leaving significant upside.
Economic assessment and financials
Preliminary Economic Assessment (PEA) confirms robust economics: NPV (8% pre-tax) of A$377M, IRR 37%, 10-year mine life, 4-year payback for stand-alone processing.
Stand-alone plant: A$266M capex, LOM EBITDA A$981M, LOM free cash flow A$693M.
Toll treating option: lower capex (A$98M), NPV8 A$362M, IRR 67%, 2-year payback, LOM EBITDA A$723M.
At spot prices, NPV increases to A$533M (onsite) and A$518M (toll), with IRRs of 48% and 88% respectively.
Average annual EBITDA at steady state projected at A$130M; AISC: $30.18 (onsite), $36.43 (toll).
Production profile and revenue
10-year schedule with 1.2 Mtpa production; steady output of 3.0 Moz silver, 38kt lead, 1.4kt copper, 3.8koz gold annually (5.4 Moz AgEq).
LOM production: 22.7 Moz silver, 285kt lead, 5.8kt copper, 34koz gold; total revenue A$2,193M, with 53% from silver and 39% from lead.
First four years of production (payback period) underpinned by 82% indicated resources.
Latest events from Maronan Metals
- Loss narrowed, cash reserves strengthened, and key project milestones advanced.MMA
H1 202618 Feb 2026 - Advancing a major silver project in Queensland with strong economics and significant growth potential.MMA
RIU Explorers Conference 202618 Feb 2026 - Scalable silver project with strong economics, flexible development, and advanced permitting.MMA
Investor presentation11 Feb 2026 - Secured key approvals, raised $17.6M, and achieved strong gold and silver recoveries.MMA
Q2 2026 TU28 Jan 2026 - Half-year loss increased to $6.88M as exploration ramped up; cash reserves at $5.4M.MMA
H1 202529 Dec 2025 - Resource base doubled, net loss widened, and mine development steps advanced.MMA
H2 202529 Dec 2025 - Strong PEA shows A$377m NPV, 37% IRR, and scalable resource growth potential.MMA
AGM 2025 Presentation25 Nov 2025 - Large silver-lead and copper-gold resources drive a staged growth strategy toward production.MMA
Noosa Mining Investor Conference16 Nov 2025 - PEA shows strong project economics; $16M raised post-quarter to advance development.MMA
Q1 2026 TU27 Oct 2025