Mayfair Gold (MFG) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
12 Aug, 2026Project overview and strategy
Advancing the Fenn-Gib gold project in Ontario with a 4.3 Moz indicated gold resource and 0.1 Moz inferred resource, targeting a quick path to production and free cash flow by 2030.
Strategic focus on lower capital requirements, accelerated provincial permitting expected by 2028, and targeting high-margin material for improved payback.
Project located in the prolific Timmins gold district, with excellent infrastructure, workforce access, and proximity to established producers.
Management and board have a strong track record, with ~35% insider ownership and significant insider equity purchases since October 2024.
Project economics and financials
2026 PFS outlines a 1 Moz reserve at US$3,100/oz gold, with a 14.3-year mine life, 4,800 tpd throughput, and initial capex of C$450M.
Life-of-mine average annual gold production is 64,096 oz at 1.29 g/t, with years 1-6 averaging 71,336 oz at 1.47 g/t and 90% recoveries.
LOM average AISC is US$1,292/oz, with after-tax NPV (5%) of C$652M (base case) and C$1,373M (spot case), IRR of 24% (base) and 38% (spot), and payback of 2.7 years (base) or 1.7 years (spot).
Cumulative free cash flow projected at C$1.7B (base) to C$2.9B (spot), with annual FCF sensitivity to gold price.
Technical highlights and de-risking
Near-surface high-grade starter zone enables early payback and robust early economics, with grade control drilling validating the resource model and identifying high-grade upside.
Modular build and <5,000 tpd design reduce execution risk and keep project within Ontario environmental approval thresholds.
Metallurgical testwork confirms predictable recoveries (80–90%) and supports a conventional flowsheet with future gravity recovery potential.
Capex breakdown: process plant (26%), on-site infrastructure (16%), contingency (15%), owner's cost (14%), with sustaining capex of C$61M.
Latest events from Mayfair Gold
- Q2 2026 results show strong progress on Fenn-Gib, targeting high-grade gold reserves and robust cash flow.MFG
Q2 2026 - Seeking up to C$250M for Fenn-Gib Project advancement; no revenues, high risk, flexible offering.MFG
Registration filing - Q1 2026 results show strong progress at Fenn-Gib, targeting 2028 construction and 2030 production.MFG
Q1 2026 - Pre-revenue gold explorer aims to raise up to C$250M for project development amid high risks.MFG
Registration filing - PFS confirms robust economics for Fenn-Gib, with $652M NPV, 24.1% IRR, and $38.2M cash at year-end.MFG
Q4 2025 - Accelerated gold project development aims for rapid free cash flow and strong returns.MFG
Investor presentation - Q2 2024 featured a new board, ongoing Fenn-Gib development, and a $5.71M net loss.MFG
Q2 2024 - Advanced Fenn-Gib project studies, updated resources, and raised $6M to support development.MFG
Q3 2024 - Q4 2024 saw project advancement, a $2.23M loss, and $6M raised for Fenn-Gib development.MFG
Q4 2024