Mayfair Gold (MFG) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
12 Nov, 2026Executive summary
Fenn-Gib advanced toward a 2028 construction target and initial production in 2030; no operating revenue had been generated.
Q3 2026 net loss was $8.20M and 9M net loss was $22.87M, compared with $2.24M and $6.17M in the prior-year periods.
September 30 cash and cash equivalents were $15.64M; pro forma liquidity was C$25.6M after Macquarie’s October investment.
Financial highlights
Q3 operating expenses were $8.31M versus $2.32M YoY; 9M expenses were $23.36M versus $6.35M.
9M exploration and evaluation expense was $14.68M and G&A was $6.37M; Q3 amounts were $4.72M and $2.13M, respectively.
9M share-based payment expense was $2.27M versus $598,945 YoY; interest income was $526,798 versus $158,400.
Total assets were $34.60M at September 30, down from $53.27M at December 31, 2025.
Outlook and guidance
The 2026 PFS estimates C$450M initial capital, a 2.7-year base-case payback and $896M cumulative free cash flow over the first six production years at US$3,100/oz gold.
PFS forecasts average annual production of 71.3 koz in the first six years and 920 koz over a 14.3-year mine life; construction is targeted for 2028 and initial production for 2030.
The PFS outlines a near-surface, higher-grade 1.0 million oz probable reserve within a 4.3 million oz indicated resource.
Q4 priorities include selecting detailed engineering, advancing procurement, awarding long-lead equipment contracts, and completing site investigations and final condemnation drilling.
Latest events from Mayfair Gold
- A 1Moz starter plan targets 2030 production, leaving 3.3Moz indicated for growth.MFG
Corporate presentation - Timmins gold project targets rapid permitting and high early cash flow with strong team and modular build.MFG
Mining Forum Americas 2026 - Fenn-Gib targets 2030 production with robust economics, rapid payback, and major exploration upside.MFG
Company presentation - Fenn-Gib targets 2030 production with strong economics, high-grade resource, and rapid permitting.MFG
Investor presentation - Q2 2026 results show strong progress on Fenn-Gib, targeting high-grade gold reserves and robust cash flow.MFG
Q2 2026 - Seeking up to C$250M for Fenn-Gib Project advancement; no revenues, high risk, flexible offering.MFG
Registration filing - Q1 2026 results show strong progress at Fenn-Gib, targeting 2028 construction and 2030 production.MFG
Q1 2026 - Pre-revenue gold explorer aims to raise up to C$250M for project development amid high risks.MFG
Registration filing - PFS confirms robust economics for Fenn-Gib, with $652M NPV, 24.1% IRR, and $38.2M cash at year-end.MFG
Q4 2025