New Found Gold (NFG) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
29 Oct, 2026Production growth and assets
Hammerdown entered commercial production at 700 tons/day; output projected at 20,000–25,000 oz/year, with CAD 2,500 AISC and CAD 35–40 million annual cash flow for G&A and exploration.
Pine Cove mill expansion from 700 to 1,400 tons/day is underway, including conversion from flotation Merrill-Crowe to gravity CIL; expansion targeted for Q4 2027.
Queensway first ore targeted for Q4 2027; production expected above 70,000 oz/year, with combined output targeting ~100,000 oz/year in 2028–2030 and 200,000 oz/year by 2031.
Queensway plan phases development: 700 tons/day with offsite processing first, then a site mill and expanded production; phase one CapEx CAD 155 million, phase two CAD 442 million.
Funding and project economics
At end-Q2, cash was CAD 194 million; April financing totaled CAD 220 million, comprising CAD 115 million equity and CAD 105 million debt, with CAD 35 million debt availability through April 2027.
CAD 17 million in warrants due through September 2027 were described as well in the money; Hammerdown cash flow is projected to fund Queensway CapEx, with CAD 88 million projected cash at end-2027.
Queensway base case used CAD 2,500 gold; a cited CAD 3,300 upside case showed CAD 1.5 billion NPV and 200% return.
Development milestones and execution
Queensway updated mineral resource estimate and technical report expected in the coming weeks; environmental assessment targeted for early 2027, groundbreaking in Q2 2027, and first ore in Q4 2027.
Phase two to advance through feasibility study, permit application and detailed engineering; Pine Cove expansion relies on construction execution and remaining permitting, concrete and building milestones.
Queensway phase one includes a 4.5 km mine-plan strike; the larger property package spans 110 km, with a 1.5 km by 300 m Dropkick zone drilled in 2025 for inclusion in the upcoming resource update.
Latest events from New Found Gold
- A fully funded Queensway build targets 1.7 Moz over 15 years at US$1,375/oz LOM AISC.NFG
Corporate presentation - Hammerdown reached commercial production as Queensway targets Phase I feed in Q4 2027.NFG
Q3 2026 - Fully funded for rapid gold production growth in Newfoundland with strong resource upside.NFG
Corporate presentation - Q2 2026 financials filed; production projects advance; TSX listing approval received.NFG
Q2 2026 - Fully funded, advancing high-grade gold projects with strong economics and exploration upside.NFG
Corporate presentation - Annual report confirms strong governance, effective controls, and highlights key exploration risks.NFG
Q4 2024 - Aggressive exploration, resource growth, and production plans signal strong near-term value creation.NFG
2025 Precious Metals Summit - Zurich - Accelerated by a key acquisition, high-grade gold production is set to start by next year.NFG
38th Annual Roth Conference - Merger forms a Canadian gold producer with near-term cash flow, synergies, and growth upside.NFG
M&A Announcement