Executive summary

  • Hammerdown achieved commercial production on August 19, 2026; Q3 output was 4,863 oz of gold and year-to-date production was 10,670 oz.

  • Queensway’s revised PEA and updated resource estimate were announced after quarter-end; its Phase I Environmental Preview Report entered public review.

  • More than 328,000 person-hours were worked at Hammerdown and Pine Cove through September 30 with zero lost-time incidents.

Financial highlights

  • Q3 revenue was $41.6M from 6,935 oz sold at an average realized price of US$4,285/oz; year-to-date revenue was $67.2M.

  • Q3 mine operating income was $18.6M, or 45% of revenue; EBITDA was $13.1M.

  • Q3 net loss was $7.1M, or $0.02/share, versus $12.9M, or $0.06/share, in Q3 2025; year-to-date net loss was $37.3M.

  • Q3 operating cash flow before working-capital changes was $11.2M; cash used in operating activities was $6.8M.

Outlook and guidance

  • Queensway Phase I targets first mineralized material delivery to Pine Cove in Q4 2027; contractor mobilization is planned for Q1, early works for Q2 and mining for Q3 2027, subject to permits.

  • Hammerdown’s permanent crusher and sorter is targeted for substantial completion in Q4 2026, with commissioning and ramp-up in Q1 2027.

  • Pine Cove expansion to 1,400 tpd and Gravity-CIL conversion are targeted for Q4 2027; test work indicates Hammerdown recovery could rise to ~92%.

  • Queensway Phase I initial capital is estimated at $149.8M and is described as fully funded; the plan anticipates first-phase cash flow funding later phases.

Partial view of Summaries dataset, powered by Quartr API