Nordic Mining (NOM) Q2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2024 earnings summary
9 Jul, 2026Executive summary
Engebø Project construction is progressing on schedule, with commissioning underway and production ramp-up planned for Q4 2024; NOK 2.3 billion invested to date and all major equipment installations and civil works completed.
No lost time injuries reported, maintaining a strong safety record over 250,000 working hours and 854 LTI-free days.
Five-year mining operator agreement secured with Sunnfjord Industripartner; co-branding agreement with Barton Group for garnet offtake enhances market reach.
Project fully financed with USD 277 million, including final NOK 48 million drawdown and all major EPC contracts activated.
Sole ownership of Kvinnherad quartz deposit established, with ongoing test work, partner discussions, and environmental/social impact studies.
Financial highlights
NOK 385 million invested in Engebø during Q2 2024, with total accumulated investment reaching NOK 2.3 billion.
NOK 41.3 million transferred from mine under construction to property, plant, and equipment after completion of the administration building.
Cash and cash equivalents at quarter end were NOK 409 million, with NOK 306 million allocated to Engebø and NOK 508 million in restricted bond escrow.
Final $48 million bond escrow released in August, ensuring full project funding.
Q2 net profit of NOK 10.3 million due to FX gains, despite operating loss; H1 2024 net loss was NOK -30.5 million, improved from NOK -57.1 million year-over-year.
Outlook and guidance
Production ramp-up at Engebø scheduled for Q4 2024, with full production capacity targeted during 2025.
Remaining project reserve estimated at $25 million, covering minimum liquidity and unexpected costs.
Rutile prices are slightly above forecast, with expectations of further price increases due to global supply drops.
Titanium metal segment outlook remains strong, driven by projected growth in aircraft production and robust demand.
Third-party assessments confirm sufficient funding and on-time completion.
Latest events from Nordic Mining
- Commissioning nearly complete; Q4 ramp-up and full financing secured, with Q3 net profit of NOK 10m.NOM
Q3 20248 Jul 2026 - Ramp-up at Engebø improved output but widened losses and increased liquidity risks.NOM
Q1 202612 May 2026 - Q4 2025 saw record garnet, first rutile, and new funding, with steady-state targeted for 2026.NOM
Q4 20254 Feb 2026 - Construction complete, ramp-up underway, first shipments in 2025, strong funding position.NOM
Q4 202416 Dec 2025 - First garnet shipment and net profit highlight ramp-up progress; steady-state eyed by year-end.NOM
Q1 202525 Nov 2025 - First garnet revenues and ramp-up progress, with strong liquidity and ongoing legal uncertainty.NOM
Q2 202523 Nov 2025 - Ramp-up delays caused a NOK 144.8M net loss, but liquidity is secure and demand remains strong.NOM
Q3 20253 Nov 2025