Nordic Mining (NOM) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
18 Aug, 2026Executive summary
Engebø facility has transitioned to ramp-up phase after over NOK 3 billion investment, with throughput near design capacity but mineral recovery and product quality below plan, impacting sales and revenue recognition.
Operational progress is slower than expected, with technical and quality challenges delaying income and increasing costs.
Regulatory uncertainty persists after the Supreme Court invalidated the discharge/tailings permit; operations continue under existing conditions pending a temporary permit decision expected in September.
Immediate liquidity needs are acute, with ongoing efforts to secure both short-term financing and long-term capital restructuring.
Engebø is positioned as a strategic, long-life asset and key European supplier of rutile and garnet.
Financial highlights
No revenue recognized in Q2 2026 due to product quality and shipment disputes; operating loss was NOK 154–154.3 million, net loss NOK 223.1 million.
Operating expenses were NOK 122.1 million, with one-off NOK 10 million penalty provision for Barton.
Cash and cash equivalents at quarter-end were NOK 149.6–150 million; equity ratio at 25.6–26%.
Net cash flow from operating activities for H1 2026 was NOK -246.7 million; negative cash flow for Q2 was NOK 210 million.
Total assets at 30 June 2026 were NOK 3.1–3,112 million; total liabilities NOK 2,317 million.
Outlook and guidance
Full run-rate production is delayed, with a more conservative production profile and ramp-up/operational improvements prioritized.
Total liquidity need through 2027 is NOK 475 million, with immediate requirement of USD 10–15 million by early September.
Targeting long-term financing solution before November coupon payment; constructive discussions ongoing with bondholders and stakeholders.
Market fundamentals for rutile and garnet remain supportive, with constrained supply.
Latest events from Nordic Mining
- Ramp-up at Engebø improved output but widened losses and increased liquidity risks.NOM
Q1 2026 - Q4 2025 saw record garnet, first rutile, and new funding, with steady-state targeted for 2026.NOM
Q4 2025 - Ramp-up delays caused a NOK 144.8M net loss, but liquidity is secure and demand remains strong.NOM
Q3 2025 - First garnet revenues and ramp-up progress, with strong liquidity and ongoing legal uncertainty.NOM
Q2 2025 - Commissioning nearly complete; Q4 ramp-up and full financing secured, with Q3 net profit of NOK 10m.NOM
Q3 2024 - Project fully funded, on schedule for Q4 2024 ramp-up, and maintains strong safety record.NOM
Q2 2024 - Construction complete, ramp-up underway, first shipments in 2025, strong funding position.NOM
Q4 2024 - First garnet shipment and net profit highlight ramp-up progress; steady-state eyed by year-end.NOM
Q1 2025