Oklo (OKLO) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
11 Aug, 2026Executive summary
Achieved first criticality at the Groves isotope facility in under a year, setting a record for privately funded, full-scale nuclear deployment.
Advanced Aurora-INL, Ohio clean energy campus, and Eielson Air Force Base projects, with key regulatory milestones and customer agreements secured.
Strengthened vertical integration across power, fuel, and isotopes, supported by acquisitions of ARMEC and Creative Engineers, Inc.
Expanded manufacturing, engineering, and sodium systems expertise through acquisitions and partnerships.
Demonstrated execution capabilities, reducing future project risk and enabling repeatable, scalable deployment.
Financial highlights
Year-to-date net loss for Q2 2026 was $81.6 million, with a loss from operations of $124.2 million, offset by $44.5 million in net interest and dividend income.
Cash used in operating activities was $65.5 million; investing activities used $912.7 million, including $743.6 million for marketable securities and $126.9 million for property, plant, and equipment.
Ended Q2 with $3.0 billion in cash and marketable securities, including $1.9 billion raised via ATM programs in 2026.
Revenue for Q2 2026 was $1.2 million, primarily from recent acquisitions.
Net loss per share for the six months ended June 30, 2026: $(0.47); weighted-average shares outstanding: 173.3–176.2 million.
Outlook and guidance
Capital spending expected to be weighted toward the second half of 2026, with increased visibility into procurement, construction, fuel, and project payment milestones.
Aurora-INL remains on track for 2028 startup, with proactive capital deployment to secure long-lead items and ensure project delivery.
First isotope revenue anticipated from the Idaho Radiochemistry Lab in early 2027, with Groves ramping up R&D production over the next year.
2026 cash use guidance: $120–$150 million for operating activities and $400–$500 million for capital expenditures.
Management believes current liquidity is sufficient for at least the next year.
Latest events from Oklo
- Vertically integrated nuclear platform leverages proven tech, recycling, and isotopes for growth.OKLO
Corporate presentation - Q1 2026 net loss was $33.1M, with liquidity rising to $2.54B after a $1.2B equity raise.OKLO
Q1 2026 - Director elections, auditor ratification, and strong governance highlight this year's proxy.OKLO
Proxy filing - Advanced project deployment, secured Meta prepayment, and ended 2025 with $1.4B in liquidity.OKLO
Q4 2025 - At-the-market equity offering of up to $400M supports advanced nuclear growth strategy.OKLO
Registration Filing - Up to $400M in common stock offered to fund growth in advanced nuclear power and fuel recycling.OKLO
Registration Filing - Q3 saw regulatory progress, a $25M acquisition, and a 2.1 GW customer pipeline.OKLO
Q3 2024 - Customer pipeline doubled to 1,400 MW, $294.6M cash, Q2 net loss $29.3M, first plant in 2027.OKLO
Q2 2024 - Secured a 12 GW power deal, expanded pipeline to 14 GW, and ended 2024 with $275M cash.OKLO
Q4 2024