Orezone Gold (ORE) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
2 Oct, 2026Operating outlook
Multi-mine operation across Burkina Faso and Quebec; 2026 production guidance of 230,000–240,000 oz from two operations, with production expected to grow in coming years.
Bomboré 2026 production guidance of 160,000–180,000 oz; management expects costs at the lower end of guidance.
Bomboré has 2.4 Moz of resources to an average depth of 37 m and 5 Moz to approximately 75 m; 100,000 m of drilling added, with a new resource, reserve and mine plan targeted for end-Q1 2027.
Hard-rock mill throughput reached 4,700 t/d; management expects to run at 4,400 t/d after mill adjustments.
Casa Berardi operations and exploration
Casa Berardi life-of-mine plan outlines 14 years of open-pit and underground production, averaging 116,000 oz/year at AISC just under CAD 1,900/oz.
Drilling underway: approximately 70,000 m planned in 2026 and more than 100,000 m targeted in 2027; underground development is running at 17 m/day, with 20 m/day an aspiration.
Exploration targets include higher-grade zones below pits, the north side of the Casa Berardi Fault and underexplored Abitibi ground; further drill results were expected in coming weeks.
A regional exploration program is planned over winter 2026, with results expected in Q2 2027; 37 km of the Casa Berardi fault and belt are held.
Casa Berardi produced more than 3.2 Moz over 30 years, with 3 Moz of resources remaining; management targets production above 150,000 oz/year beyond 2033 through reinvestment and mine-life extensions.
Heva-Hosco development
Heva-Hosco lies on the Cadillac-Larder Lake Break; a new PEA was targeted for October 2026, based on a 3 Mtpa mill, following successful metallurgical test work.
Feasibility work is planned after the PEA, with a construction decision targeted for end-2027 to early 2028.
Latest events from Orezone Gold
- Casa Berardi targets 1.63Moz gold over 14 years with strong growth, exploration, and re-rating potential.ORE
Corporate presentation - Record Q2 gold output and financials, with expansion and improved H2 outlook expected.ORE
Q2 2026 - Record Q1-2026 earnings and production growth achieved after Casa Berardi acquisition.ORE
Q1 2026 - 2026 gold production forecast at 220,000–240,000oz, with major growth from Casa Berardi and Bomboré.ORE
Corporate presentation - Record 2025 results and Casa Berardi acquisition drive strong 2026 growth outlook.ORE
Q4 2025 - Acquisition of Casa Berardi Mine creates a diversified, growth-focused gold producer in Canada.ORE
M&A announcement - Record cash flow and expansion progress offset lower gold output and higher costs in Q3-2024.ORE
Q3 2024 - Q2-2024 output fell and costs rose, but grid stability and expansion support a stronger H2.ORE
Q2 2024 - Q1 2025 saw record revenue, strong liquidity, and major expansion progress.ORE
Q1 2025