Osisko Gold Group (OGG) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
12 Nov, 2026Investment overview
Positioning centers on developing Cariboo into a major Canadian gold mine, with construction underway, permitted assets, district-scale potential and a stated focus on stakeholder partnerships.
Cariboo is 100% owned in British Columbia; its 2025 feasibility study outlines a 10-year mine life and production of up to 223 koz/year.
Formal construction decision made in September 2026; first gold pour is targeted for Q1 2029 and commercial production for H2 2029.
Cariboo development and funding
Go-forward capital obligation is C$990M; estimated sources total C$1.7B, including C$879M in cash, with project completion estimated at 22% as of July 31, 2026.
Detailed engineering was ~40% complete; procurement and long-lead commitments were ~44% complete, with C$325M committed as of the update.
Funding slide presents US$1.3B in sources versus US$1.1B in uses, including US$600M senior notes proceeds and a US$120M Trafigura term loan facility.
More than US$1.3B was raised since August 2025, including US$466M equity, US$260M convertible notes net of capped-call cost and US$600M senior notes.
More than 350 personnel were advancing site pre-construction; work included underground development, water treatment, waste storage, sediment control, earthworks and portal excavation.
Cariboo economics and operating plan
2026 go-forward update estimates 190 koz/year LOM average production, 202 koz/year in the first five years, a 10-year mine life and US$1,163/oz AISC.
At US$3,570/oz gold and 1.38 FX, after-tax NPV5% is C$2.32B and IRR 34.7%; at US$4,350/oz, NPV5% is C$3.18B and IRR 42.7%.
At those respective gold-price assumptions, average annual FCF is C$362M and C$485M over LOM, and C$521M and C$642M in the first five years.
Mine plan uses three areas with aggregate ore feed of 4,900 tpd; LOM recovery is 92.6%, with gravity recovery expected to produce 46% of gold as doré.
13,684 m of Lowhee infill drilling broadly validated model assumptions; preliminary internal reconciliation showed localized variation in tonnes, ounces and grades.
Latest events from Osisko Gold Group
- Cariboo construction is underway, with first gold targeted for Q1 2029 and $907 million remaining cost estimate.OGG
Q3 2026 - Aggressive mine build and drilling aim to double gold output and resource base by 2029.OGG
Mining Forum Americas 2026 - Revenue surged and operating income turned positive as gold sales and project development accelerated.OGG
Q2 2026 - Cariboo Gold Project targets 190 koz/year with strong economics and major exploration upside.OGG
Investor presentation - Cariboo Gold is on track for major growth, with robust funding, drilling, and top-tier mine ambitions.OGG
John Tumazos Very Independent Research 2026 Virtual Conference - Cariboo Gold Project advances toward production with strong financing, low costs, and growth potential.OGG
Investor presentation - US$300M convertible notes and capped call offer flexible, low-cost funding and dilution protection.OGG
Investor presentation - Cariboo Gold Project advances toward top-tier gold production with strong economics and growth potential.OGG
Investor presentation - $594.3M cash, Cariboo Gold Project resumed, $143.8M US raised, Tintic gold sales $2.2M.OGG
Q1 2026