Investor presentation
Logotype for Osisko Gold Group Inc

Osisko Gold Group (OGG) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Osisko Gold Group Inc

Investor presentation summary

12 Nov, 2026

Investment overview

  • Positioning centers on developing Cariboo into a major Canadian gold mine, with construction underway, permitted assets, district-scale potential and a stated focus on stakeholder partnerships.

  • Cariboo is 100% owned in British Columbia; its 2025 feasibility study outlines a 10-year mine life and production of up to 223 koz/year.

  • Formal construction decision made in September 2026; first gold pour is targeted for Q1 2029 and commercial production for H2 2029.

Cariboo development and funding

  • Go-forward capital obligation is C$990M; estimated sources total C$1.7B, including C$879M in cash, with project completion estimated at 22% as of July 31, 2026.

  • Detailed engineering was ~40% complete; procurement and long-lead commitments were ~44% complete, with C$325M committed as of the update.

  • Funding slide presents US$1.3B in sources versus US$1.1B in uses, including US$600M senior notes proceeds and a US$120M Trafigura term loan facility.

  • More than US$1.3B was raised since August 2025, including US$466M equity, US$260M convertible notes net of capped-call cost and US$600M senior notes.

  • More than 350 personnel were advancing site pre-construction; work included underground development, water treatment, waste storage, sediment control, earthworks and portal excavation.

Cariboo economics and operating plan

  • 2026 go-forward update estimates 190 koz/year LOM average production, 202 koz/year in the first five years, a 10-year mine life and US$1,163/oz AISC.

  • At US$3,570/oz gold and 1.38 FX, after-tax NPV5% is C$2.32B and IRR 34.7%; at US$4,350/oz, NPV5% is C$3.18B and IRR 42.7%.

  • At those respective gold-price assumptions, average annual FCF is C$362M and C$485M over LOM, and C$521M and C$642M in the first five years.

  • Mine plan uses three areas with aggregate ore feed of 4,900 tpd; LOM recovery is 92.6%, with gravity recovery expected to produce 46% of gold as doré.

  • 13,684 m of Lowhee infill drilling broadly validated model assumptions; preliminary internal reconciliation showed localized variation in tonnes, ounces and grades.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Osisko Gold Group