Osisko Gold Group (OGG) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
29 Sep, 2026Project overview and resource update
$270 million spent pre-FID; 2 million oz reserves, 1.61 million oz measured/indicated, 1.8 million oz inferred, with 3.6 million oz not yet in the plan but expected to be included soon.
Located near Quesnel and Prince George, with strong infrastructure and access to hydroelectric power, minimizing diesel reliance.
Historic mining area with over 1,000 workings; only 4.4 km of 86 km strike length explored in detail, with 6 km more underway.
CAD 990 million ($717 million) investment planned, with CAD 1.6 billion cash available and CAD 700 million free board for aggressive mine build and resource integration.
Construction progress and mine development
Construction is 22% complete, with two portals underway and detailed engineering at 40%.
CAD 325 million committed to procurement; mill and mining fleet already procured and on site.
350-person camp, waste dump, and water treatment plant nearly complete; significant earthworks finished.
Mill site nearing completion, with concrete work about to start; second portal collaring in progress.
Production targets and financials
Initial production target of 200,000 oz/year starting Q1 2029, with plans to double to 400,000 oz/year through conversion drilling.
Ten-year mine life, all-in sustaining cost of $1,163/oz, and free cash flow of CAD 362 million/year at $3,700 gold.
NPV ranges from CAD 2.3 billion at $3,570 gold to CAD 3.8 billion at $4,300 gold; IRR between 34.7% and 43%.
Payback period of 1.8 years; annual free cash flow first five years at CAD 642 million.
Latest events from Osisko Gold Group
- Cariboo construction is underway, with first gold targeted for Q1 2029 and $907 million remaining cost estimate.OGG
Q3 2026 - Cariboo construction is underway, targeting first gold in Q1 2029.OGG
Investor presentation - Revenue surged and operating income turned positive as gold sales and project development accelerated.OGG
Q2 2026 - Cariboo Gold Project targets 190 koz/year with strong economics and major exploration upside.OGG
Investor presentation - Cariboo Gold is on track for major growth, with robust funding, drilling, and top-tier mine ambitions.OGG
John Tumazos Very Independent Research 2026 Virtual Conference - Cariboo Gold Project advances toward production with strong financing, low costs, and growth potential.OGG
Investor presentation - US$300M convertible notes and capped call offer flexible, low-cost funding and dilution protection.OGG
Investor presentation - Cariboo Gold Project advances toward top-tier gold production with strong economics and growth potential.OGG
Investor presentation - $594.3M cash, Cariboo Gold Project resumed, $143.8M US raised, Tintic gold sales $2.2M.OGG
Q1 2026