  • FY26 marked the first full construction year for the Central Lime Project after its August 2025 FID; development and customer, government and landowner arrangements advanced.

  • Priorities are safe lime commissioning, cost and funding management, and advancing the Central Cement Project toward an investment decision.

Financial highlights

  • Revenue was A$1.934m versus A$1.342m in FY25; net loss was A$27.576m versus net profit of A$271,245.

  • Operating cash outflow was A$9.055m; investing cash outflow was A$18.125m, including A$54.912m of mine development payments offset by A$41.140m in term-deposit and treasury-bill recoupments.

  • FY26 cash payments for exploration and development were A$58.9m; cash and cash equivalents were A$16.724m at 30 June 2026.

Outlook and guidance

  • First lime production is targeted from Kiln 1 between end-Q1 and Q2 CY2027; both kilns are targeted for completion in Q2 CY2027.

  • Central Cement FID is targeted for Q1 CY2027, subject to feasibility, environmental and social requirements, financing and commercial arrangements.

  • Preferred EPC tenderer approval for Central Cement is targeted by 18 December 2026; early works are targeted for the December 2026 quarter.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Pacific Lime and Cement Limited