29 Oct, 2026Strategic precinct
Completed strategic planning for a 4,500 ha gazetted SEZ and multi-berth port, 35 km from Port Moresby and 7 km from PNG LNG.
The precinct includes 99-year State leases held through 50:50 joint ventures with landowner companies; 3,678 ha are classified as usable land.
Qualifying SEZ businesses may receive 10 years of exemptions from corporate tax, dividend withholding tax, foreign contractor withholding tax and import duties.
The port is under construction to ISPS standards; tenant documentation and sublicensing arrangements are authorised by the SEZ Authority.
Anchor projects and funding
Central Lime and Central Cement remain the capital and management priorities; SEZ land, leases and port infrastructure are principally intended to support them.
Next steps include completing the quicklime plant’s first phase, targeted for Q1 2027, and delivering the cement plant.
The stated funding model assigns anchor plants and the land-and-port platform to PLC, enabling infrastructure to potential DFIs, and cluster plant capex to tenants and strategic investors.
DFI discussions on port and utility infrastructure funding are non-binding; further precinct development is expected to rely largely on third-party tenants and investors.
Port and tenant opportunities
Indicative plans phase the precinct from 560 ha short term to 1,603 ha medium term and 3,017 ha long term, with port and heavy industry leading initial development.
Target clusters span lime and cement, gas and energy, fuel storage, fabrication, logistics, data centres, small and medium industry, and urban services; development depends on tenant demand and funding.
Indicative port throughput reaches ~7.2 Mt annually by 2060 excluding liquid bulk, or ~30 Mt including it; the higher case depends on energy projects, including a gas agreement.
Flagship concepts include an 11.25 million-barrel strategic fuel reserve, gas-based fertiliser and chemicals, a cyber campus, steel fabrication and an industry park; each depends on stated conditions or tenant demand.
Latest events from Pacific Lime and Cement Limited
- Central Lime advances toward CY2027 production within its funding envelope as cement tendering progresses.PLA
Q1 2027 TU - Lime-project momentum meets a A$27.6m loss and material funding uncertainty.PLA
H2 2026 - Construction milestones, PNG equity investment, and funding secure project to Q1 2027 production.PLA
Q4 2026 TU - Integrated lime and cement project in PNG targets regional supply gaps with strong government and IFC backing.PLA
Investor presentation - Achieved FID for Central Lime Project, first quicklime sales, and returned to profitability.PLA
H2 2025 - Equity raising secures funding for scalable lime and cement project with strong market demand.PLA
Corporate Presentation - A$100.1 million raised, projects fully funded, and major construction milestones achieved.PLA
Q3 2025 TU - Shareholders raised governance and diversity issues, with all resolutions voted online and results pending.PLA
AGM 2024 - Project funding, legal wins, and capital raises drive early revenue and asset growth.PLA
H2 2024