12 Nov, 2026Equity raise and funding
Fully underwritten A$525m raise: A$474m ASX placement and C$50m (~A$51m) TSX bought deal; ASX price A$7.80, 10.3% below the 11 Nov close; non-underwritten SPP targets up to A$50m.
Proceeds target US$252m for PLS CY2027–28 development, US$30m for Triple R resource growth and mine-life extension, US$40m for Athabasca exploration, US$28m for balance-sheet flexibility and US$11m for offer costs.
PLS allocation of A$367m includes ~A$300m in the stated $1.36bn project capital estimate; half to two-thirds of the raise is expected to be spent before FID.
Funds support early procurement of long-lead equipment, infrastructure and production slots, early works, detailed engineering, site readiness and project execution ahead of FID.
Project-finance discussions are progressing; lenders will assess debt sizing and minimum revenue requirements next year. Contracted revenue is expected by FID; corporate debt and a strategic partner remain options, alongside debt repayment.
PLS development and permitting
PLS targets ~9Mlb U3O8 annual production over an initial 10-year mine life, with first production targeted for 2031, subject to seasonal, regulatory and investment approvals.
CNSC hearing and decision are targeted by end-CY2027 or very early 2028; FID is expected in early CY2028.
FEED is refining engineering detail without changing scope; a refreshed capital estimate is expected by Q1 2027, with increases anticipated mainly from inflation and refined detail.
Provincial EIS and NROC permitting advanced; three of four mutual benefit agreements are concluded, with the Métis Nation–Saskatchewan agreement outstanding. A judicial review of Saskatchewan’s approval could delay development, add costs or restrict activities.
The 28 Aug 2025 study reported post-tax NPV of US$1,325m and IRR of 28.2% at US$90/lb uranium, with 9.1Mlb average annual production over the initial 10-year mine life.
Langer Heinrich operations
October 2026 performance improved against the September quarter as mining advanced through J Pit and higher-grade ore reached the plant; operations showed annualized total movement of 8.5Mt, recovery in the high 80s and grades above 500.
FY2027 guidance remains unchanged: production 5.1–5.6Mlb U3O8, sales 4.8–5.3Mlb, cost of production US$44–48/lb and capital expenditure US$29–35m. Q2 was expected to meet or slightly exceed Q1, with a second-half production uplift targeted; kiln shutdown timing shifted due to shipping delays, with no guidance impact.
Latest events from Paladin Energy
- FY2027 guidance held as Langer Heinrich targets an H2 recovery and PLS advances toward FID.PDN
Q1 2027 - Langer Heinrich ramp-up and PLS advances drive robust growth, resource expansion, and strong financials.PDN
Investor Day 2026 - Revenue up 71% and net cash surged as Langer Heinrich ramped up and PLS advanced.PDN
H2 2026 - Exceeded FY2026 guidance, advanced PLS milestones, and strengthened position in uranium market.PDN
Q4 2026 - Production ramp-up and high-grade projects target global uranium supply gaps amid rising demand.PDN
Energy & Precious Metals Virtual Investor Summit - A$300 million equity raise to fund PLS Project advancement and LHM ramp-up.PDN
Investor Update - Langer Heinrich Mine ramp-up, Fission acquisition, and ESG focus drive 2024 strategy.PDN
AGM 2024 - All-scrip merger forms a global uranium leader with a 30% premium for Fission holders.PDN
M&A Announcement - Record uranium output and resilient recovery highlight strong operational and financial performance.PDN
Q3 2025