FY09-10 marked a shift from project development to power generation, with the first 300 MW Rosa unit entering commercial operation on March 12, 2010.
The planned generation portfolio was approximately 35,000 MW; financial closure had been achieved for nearly 10,000 MW, with construction underway across multiple projects.
Financial highlights
Consolidated total income was Rs 843.38 crore versus Rs 360.38 crore in FY08-09; net profit was Rs 683.89 crore versus Rs 244.51 crore.
Consolidated EPS was Rs 2.85 versus Rs 1.02; standalone income was Rs 3,880.73 million and standalone profit after tax was Rs 2,732.33 million.
Consolidated sale of energy was Rs 20.72 crore; investment dividends and mutual-fund redemption gains formed a substantial part of reported income.
Outlook and guidance
The second 300 MW Rosa Stage I unit was expected before its PPA schedule of June 2010; Rosa Phase II was scheduled to begin generation by March 2012.
Sasan's first unit was scheduled for March 2012; Krishnapatnam's first unit for September 2013 and full commissioning by October 2015; Tilaiya's first unit for May 2015 and full commissioning by May 2017.
Financial closure for the 3,960 MW Chitrangi project was being pursued, with most debt sanctions obtained; construction of gas projects depended on firming up gas supply.
Latest events from Reliance Power
- H1 profit improved, but subsidiary defaults and qualified reviews sustain material uncertainty.RPOWER
Q2 26/27 - Rosa’s first operating year lifted profits as a vast build-out faced fuel and execution risks.RPOWER
Q4 10/11 - Profit rose as Rosa expanded, but fuel risks and project disputes clouded growth.RPOWER
Q4 11/12 - Investment-led FY09 earnings accompanied rapid progress on a 33,480 MW project pipeline.RPOWER
Q4 08/09 - A 28,200 MW development pipeline met a large power deficit, but execution and fuel access remained pivotal.RPOWER
Q4 07/08 - Sasan’s early completion lifted capacity to 5,945 MW as fuel and project risks persisted.RPOWER
Q4 14/15 - Capacity doubled to 2,545 MW as Sasan began operations, amid fuel and project risks.RPOWER
Q4 12/13 - Capacity nearly doubled; Sasan advanced, but fuel constraints and project disputes persisted.RPOWER
Q4 13/14 - Strong plant performance offset by lower earnings, higher finance costs and project risks.RPOWER
Q4 17/18