Reliance Power (RPOWER) Q4 10/11 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 10/11 earnings summary
2 Nov, 2026Executive summary
First full year of Rosa Phase I operations drove initial operating profit; the 600 MW plant ran at over 90% PLF during the last nine months of FY11, with over 100% PLF reported after fuel and evacuation constraints eased.
Consolidated total income reached ₹1,918.03 crore versus ₹843.38 crore in FY10; net profit was ₹760.44 crore versus ₹683.89 crore, and basic and diluted EPS was ₹2.94 versus ₹2.85.
Planned generation portfolio exceeded 35,000 MW, with 600 MW operational and the rest at different development stages; associated coal mines had potential production of over 95 MTPA.
Financial highlights
Consolidated sale of energy was ₹1,023.68 crore in FY11 versus ₹20.72 crore in FY10; total income was ₹1,918.03 crore versus ₹843.38 crore.
Consolidated profit before tax was ₹771.998 crore versus ₹702.60 crore; net profit was ₹760.44 crore versus ₹683.89 crore.
Other income included ₹531.49 crore of profit on mutual fund redemptions; total other income was ₹863.27 crore.
Standalone total income was ₹471.53 crore versus ₹388.07 crore, and standalone profit after tax was ₹274.54 crore versus ₹273.23 crore.
Outlook and guidance
Target remained to reach 5,000 MW of operating capacity by 2012; Rosa Phase II (600 MW), Butibori (600 MW) and the first Sasan UMPP unit were expected by 2012.
Samalkot’s 2,400 MW open-cycle phase was expected in FY12, with the combined-cycle phase planned for the following year; its first unit was scheduled for 2011.
The 100 MW solar thermal project was scheduled for commissioning in 2013; a 40 MW solar photovoltaic project at the same site was scheduled for 2012.
Sasan mine production was expected before the first generating unit; approved Indian mine plans allowed production up to 65 MTPA, while Indonesian mine plans targeted 25 MTPA.
The 3,960 MW Tilaiya UMPP’s first unit was scheduled for May 2015 and full commissioning by May 2017; Krishnapatnam was scheduled for completion in 2015.
Latest events from Reliance Power
- H1 profit improved, but subsidiary defaults and qualified reviews sustain material uncertainty.RPOWER
Q2 26/27 - Profit rose as Rosa expanded, but fuel risks and project disputes clouded growth.RPOWER
Q4 11/12 - Rosa began generation as a 35 GW portfolio advanced amid fuel and execution risks.RPOWER
Q4 09/10 - Investment-led FY09 earnings accompanied rapid progress on a 33,480 MW project pipeline.RPOWER
Q4 08/09 - A 28,200 MW development pipeline met a large power deficit, but execution and fuel access remained pivotal.RPOWER
Q4 07/08 - Sasan’s early completion lifted capacity to 5,945 MW as fuel and project risks persisted.RPOWER
Q4 14/15 - Capacity doubled to 2,545 MW as Sasan began operations, amid fuel and project risks.RPOWER
Q4 12/13 - Capacity nearly doubled; Sasan advanced, but fuel constraints and project disputes persisted.RPOWER
Q4 13/14 - Strong plant performance offset by lower earnings, higher finance costs and project risks.RPOWER
Q4 17/18