Rio2 (RIO) 2025 Precious Metals Summit - Beaver Creek summary
Event summary combining transcript, slides, and related documents.
2025 Precious Metals Summit - Beaver Creek summary
24 Jun, 2026Project overview and resource details
Fénix Gold Project in Chile is 11 months into a 14-month construction schedule, targeting a large oxide gold resource of 4.8 million ounces at CAD 1,800 gold, with 1 million ounces inferred and 1.8 million ounces proven and probable reserves; deposit is open at depth and along strike.
Employing a staged development: initial 20,000 tons/day operation due to water restrictions, with plans to expand to 80,000 tons/day; construction is fully permitted and financed.
Project is 100% oxide with low copper and silver content, suitable for ROM heap leach processing and is the only such project in the Maricunga Gold Belt.
Management team has significant experience from previous successful projects in Peru and other mining operations.
Exploration potential remains high, with plans to use AI and big data for future drilling targets once cash flow begins.
Regional context and operational challenges
Located in the Maricunga Gold Belt, adjacent to major operations and projects, but the region is water-constrained.
Initial water solution involves trucking treated industrial water from Nueva Atacama to site, enabling ramp-up to 20,000 tons/day.
Long-term water solution is a pipeline or desalinated water from local providers, with scoping and pre-feasibility studies underway and established business relationships.
Pipeline project estimated at CAD 400 million, unlocking expansion to 80,000 tons/day and 300,000 ounces/year for over 10 years.
Infrastructure includes leaching facilities, ADR processing plant, and construction laydown areas.
Construction progress and production outlook
Camp facilities for 600 workers and leach pad construction are complete; plant commissioning set for November, with gold production targeted for January next year.
Mining will start at Fenix South, the lowest altitude pit, with recent drilling covering two years of mining material.
ROM trial achieved 75% recovery, allowing removal of the crusher from the circuit.
EIA approval received in December 2023, with ongoing permitting and financing supporting construction.
Mine expansion study and EIA for the next phase are in progress, with a PFS release targeted for February 2024.
Latest events from Rio2
- Fenix and Condestable ramp up production and expansion, targeting self-funded growth.RIO
Mining Forum Europe 202624 Jun 2026 - Expanding gold and copper production with robust EBITDA and major growth plans in Chile and Peru.RIO
35th BMO Global Metals, Mining & Critical Minerals Conference20 Jun 2026 - Q1 2026 saw first gold from Fenix and strong Condestable results, boosting revenue and earnings.RIO
Q1 20261 Jun 2026