Rox Resources (RXL) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
9 Nov, 2026Development and delivery
Construction and underground development advancing; stoping commenced at United North, with mining underway in all three declines.
First gold pour targeted for mid-2027; production ramp-up expected from late 2027, with an initial 7-year mine life.
Final Investment Decision reached 17 March 2026; financial close achieved in early October 2026 and first debt drawdown completed.
Funding includes A$218M equity and committed facilities of A$300M syndicated debt, A$20M cost-overrun support and A$30M bank guarantee.
Pre-commissioning stockpile target of 190kt at ~3.3g/t Au; stockpiling is underway.
DFS economics and design
DFS forecasts average production of 117kozpa and 817koz gold doré over an initial 7-year life; plant capacity is 1,000ktpa versus a 900ktpa initial mine plan.
At A$5,200/oz gold, forecast AISC is A$1,978/oz and pre-tax free cash flow is A$2.3B; at A$6,100/oz, pre-tax free cash flow is A$3.0B.
At A$5,200/oz, NPV and IRR are A$1.4B and 69% pre-tax, and A$1.0B and 55% post-tax.
Pre-production capital is A$383M; plant recovery is estimated at 90.8%, using fine grinding and atmospheric oxidation.
Resource base and growth
September 2026 estimates: Mineral Resource 12.4Mt at 5.5g/t Au for 2,195koz; Probable Ore Reserve 4.8Mt at 4.7g/t for 727koz.
DFS mine plan totals 5.7Mt at 4.9g/t Au for 900koz; the DFS production target is 817koz over 7 years.
The 150kozpa aspiration is a strategic objective, not a production target or forecast; achievement depends on resource conversion, exploration and study outcomes, among other factors.
Growth opportunity centers on using latent mill capacity and extending mine life beyond the DFS plan; the Resource is 2.2Moz versus 817koz in the DFS production profile.
DFS production target is underpinned by ~80% Indicated and 20% Inferred Resources over mine life; the first four years are ~89% Indicated and 11% Inferred.
Latest events from Rox Resources
- Youanmi construction and mining progress toward mid-CY2027 first gold, backed by new debt funding.RXL
Q1 2027 TU - Youanmi Gold Mine development fully funded and underway, targeting first gold in mid-2027.RXL
H2 2026 - First gold is targeted for mid-2027, with organic production growth potential toward 150,000 oz/year.RXL
Mining Forum Americas 2026 - High-grade gold project on track for mid-2027 production, targeting strong growth and margins.RXL
Diggers & Dealers Mining Forum 2026 - Advancing to production with high margins, robust funding, and strong growth potential.RXL
Investor presentation - Youanmi Gold Mine fully permitted, construction/mining advancing, $152.7m cash, first gold pour mid-2027.RXL
Q4 2026 TU - Fully funded gold project targets mid-2027 production with robust growth and exploration upside.RXL
Noosa Mining Conference 2026 - Fully funded and validated, the gold project targets production by mid-2027.RXL
Status update - High-margin gold project with strong economics, low costs, and major growth potential.RXL
Status update