Rox Resources (RXL) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
4 Oct, 2026Project execution and milestones
Fully funded into production: AUD 218m equity raise plus AUD 18m SPP; tier-one banks committed AUD 320m in development financing, while secured debt facilities are cited at AUD 350m.
FID made in March 2026; mill construction and ore development advancing on schedule and budget, with plant construction above 30%.
Three declines under development, first two ore levels completed and next two underway; Byrnecut Australia is the mining contractor.
High-grade stockpiles building; base plan is 190,000 tonnes at 3.3 g/t, with management expecting to exceed it.
Mill commissioning targeted for late March, first gold for mid-2027 and ramp-up to start in late 2027.
DFS plan and economics
DFS base case averages 117,000 oz/year, with 817,000 oz over an initial seven-year mine life; pre-production capital is AUD 383m.
Resource totals 2.2 Moz at 5.4 g/t; underground resource is 2.1 Moz at 6 g/t, reserve is 727,000 oz at 4.7 g/t and mine plan is 900,000 oz at 4.8 g/t.
AISC is AUD 1,978/oz (US$1,404/oz); planned metallurgical recovery is 90.8%.
DFS pre-tax NPV is AUD 1.4b (US$1.0b) and IRR 69% at base-case gold price; at current gold prices, projected pre-tax free cash flow is close to AUD 3b and payback is ~1.2 years.
Growth and exploration
Core-year production for 2029–2033 is projected to average 131,000 oz; resource and reserve growth could support 144,000–145,000 oz/year and an organic path toward 150,000 oz/year or more.
Infill, extensional and regional drilling target resource conversion, higher output and mine-life extension; one underground rig targets ~3,500 m/month, with a second planned for January alongside surface drilling.
Infill drilling returned intercepts 5–12 m wide at 15+ g/t; drilling is testing deeper extensions and high-grade plunging shoots.
Regional exploration covers a 60 km strike along the Youanmi Shear Zone; a structural analogue target is planned for early next year, and a Commonwealth resource update is assessing potential oxide mill feed.
Under-explored tenements and nearby assets within trucking distance offer resource expansion and potential bolt-on mill feed.
Latest events from Rox Resources
- Youanmi construction and mining progress toward mid-CY2027 first gold, backed by new debt funding.RXL
Q1 2027 TU - Youanmi Gold Mine development fully funded and underway, targeting first gold in mid-2027.RXL
H2 2026 - High-grade gold project on track for mid-2027 production, targeting strong growth and margins.RXL
Diggers & Dealers Mining Forum 2026 - Advancing to production with high margins, robust funding, and strong growth potential.RXL
Investor presentation - Youanmi Gold Mine fully permitted, construction/mining advancing, $152.7m cash, first gold pour mid-2027.RXL
Q4 2026 TU - Fully funded gold project targets mid-2027 production with robust growth and exploration upside.RXL
Noosa Mining Conference 2026 - Fully funded and validated, the gold project targets production by mid-2027.RXL
Status update - Well-funded and advancing toward gold production, with major milestones set for 2024.RXL
Status update - High-margin gold project with strong economics, low costs, and major growth potential.RXL
Status update