Silver Mines (SVL) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
15 Feb, 2026Project overview
Bowdens Silver Project is 100% owned and located in central New South Wales, Australia, ranking as the fifth largest undeveloped silver deposit globally.
Resource estimate stands at 180Moz Ag from 870 drill holes, with an optimised reserve of 71.7Moz Ag and an initial 16.5-year mine life averaging 4.3Moz silver per annum.
The project features significant potential for mine life extension and is situated in a low-risk jurisdiction with ready access to infrastructure.
Over 85% of project revenue is expected from silver, with additional gold and copper identified within the broader mineralised system.
The project is one of the largest globally in terms of contained silver and is among the most advanced with an up-to-date, optimised feasibility study.
Financials and capital structure
As of February 2025, 2,152.4 million shares are on issue, with a share price of $0.23 and undiluted market capitalisation of $495.1 million AUD.
Cash balance at end December 2025 was $40.5 million AUD, with an enterprise value of $454.6 million AUD.
Listed options total 66.95 million, and incentive options & rights stand at 31.7 million.
Average daily trading volume is approximately 11.2 million shares, equating to $2.4 million AUD.
Project economics and operating metrics
Pre-production capital costs are estimated at A$331 million, with a life-of-mine (LOM) all-in sustaining cost (AISC) below A$25/oz.
LOM operating margin is projected at A$948 million, with a pre-tax NPV5 of A$359 million and a payback period of 3.9 years.
The project is designed for a 16.5-year mine life, with an average output of 4.25Moz Ag per annum in the first 10 years.
LOM open pit mining cost is A$7.12/t, and LOM processing cost is A$20.78/t.
AISC over the LOM is A$24.81/oz, with sustaining costs included.
Latest events from Silver Mines
- Bowdens Silver Project DFS boosts reserves to 93.5Moz silver, confirming strong project economics.SVL
Q4 2026 TU30 Jul 2026 - A 93.5Moz silver project in NSW targets 26-year mine life, pending final permitting.SVL
Noosa Mining Conference 202627 Jul 2026 - Fully funded, advancing a top global silver project with new California exploration set for 2025.SVL
2025 Precious Metals Summit - Beaver Creek8 Jul 2026 - Strong cash position supports ongoing exploration and Bowdens Silver Project approvals.SVL
Q3 2026 TU29 Apr 2026 - Advanced Bowdens Silver Project, improved loss, secured $30.2M funding, and faced legal setback.SVL
H2 20242 Apr 2026 - Bowdens Silver Project advances toward development as capital raising and US expansion strengthen outlook.SVL
H2 20252 Apr 2026 - Loss narrowed, capital raised, and Bowdens Silver Project advanced amid regulatory progress.SVL
H1 202620 Mar 2026 - Bowdens advances as a top silver project, with DFS and permitting milestones expected in 2024.SVL
RIU Explorers Conference 202618 Feb 2026 - Record Bowdens intercept, robust cash, and regulatory progress drive project momentum.SVL
Q2 2026 TU28 Jan 2026