18 Feb, 2026Project overview and resource update
Bowdens is the fifth largest undeveloped silver project globally, with 180 million ounces of silver, 91% in measured and indicated categories.
The project has a 16.5-year mine life, averaging just under 4.5 million ounces of silver production annually.
Recent optimization released in December 2024, with a reserve of 72 million ounces.
Bowdens is highly leveraged to silver prices, with over 85% of revenue from silver at study prices and up to 93% at spot prices.
The definitive feasibility study (DFS) is expected mid-year, with potential for further mine life extension.
Financials and capital structure
Average daily trading liquidity is about AUD 2.5 million over the past two years.
Ended 2025 with over AUD 40 million in cash and AUD 8 million in in-the-money options expiring in June.
Pre-production capital costs are estimated at AUD 300–330 million, with some inflation expected.
Life-of-mine all-in sustaining cost is under AUD 25 per ounce, with current spot silver price around AUD 100.
Project development and operations
The mine is a simple five-stage open pit, with a low strip ratio and day shift mining only.
Metallurgical process shifted to a bulk concentrate, increasing recoveries and simplifying operations by removing cyanide.
Opportunities exist for underground development and debottlenecking to fill production gaps in years 6–8.
Permitting delays in New South Wales have been a challenge, but progress is now on a clear path.
Latest events from Silver Mines
- Globally significant silver project with robust economics and major exploration upside.SVL
Investor presentation15 Feb 2026 - Planning consent, full funding, and new US assets position the project for major growth.SVL
2025 Precious Metals Summit - Beaver Creek3 Feb 2026 - Record Bowdens intercept, robust cash, and regulatory progress drive project momentum.SVL
Q2 2026 TU28 Jan 2026 - Permit recovery, process optimization, and exploration drive strong project outlook.SVL
2024 Precious Metals Summit Zurich + Energy Transition14 Jan 2026 - Australia's largest silver project boasts 180Moz resource, robust margins, and major growth potential.SVL
AGM 2025 Presentation25 Nov 2025 - Raised $34M, advanced Bowdens approvals, and expanded US exploration; cash at A$43.67M.SVL
Q1 2026 TU30 Oct 2025 - Bowdens Silver Project advanced, US assets acquired, loss widened, cash and net assets increased.SVL
H2 202512 Oct 2025 - Australia's largest silver project boasts 180Moz resource, robust economics, and US growth.SVL
Investor Presentation7 Sep 2025 - Strong cash position supports ongoing project approvals and exploration across Australia and the US.SVL
Q4 2025 TU30 Jul 2025