Silver Mines (SVL) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
29 Oct, 2026Executive summary
Bowdens DFS and updated Ore Reserves support a staged development plan; Stage 1 targets 29.9Mt at 68 g/t Ag for 65.4Moz, with a 16-year initial mine plan.
The full 2026 LOM plan covers 48.2Mt over 26 years; DPHI reaffirmed its prior assessment that the project is approvable in the public interest, subject to strict consent conditions.
No mine development or production activities occurred in the quarter; quarter-end cash was A$35.06m after exploration, royalty acquisitions and property spending.
Financial highlights
2026 LOM model: revenue A$5.175bn, operating expenses A$2.785bn and operating margin A$2.390bn; pre-tax NPV5 A$1.043bn and post-tax NPV5 A$736m.
LOM post-tax IRR is 26%, with 3.0-year post-tax payback; pre-tax IRR is 31.5%.
Quarter operating cash outflow was A$0.972m and investing outflow A$37.237m, partly offset by A$37.515m financing inflow.
Placement raised A$40.271m in equity proceeds during the quarter; A$2.756m of equity issuance costs were paid.
Outlook and guidance
Stage 1 DFS models 16.75 years of operations, while Stage 2 could extend total mine life to 26 years, subject to approvals and further tailings-landform study.
IPC public hearing took place 14–16 October; determination was expected by 9 December 2026 following DPHI supplementary advice.
A 2,500m diamond drilling campaign east of the Reserve commenced to test near-pit extensions; additional drilling west of the Reserve was planned.
Latest events from Silver Mines
- DFS confirmed Bowdens as a world-class silver project with a 30% reserve increase and strong economics.SVL
H2 2026 - Bowdens Silver Project DFS boosts reserves to 93.5Moz silver, confirming strong project economics.SVL
Q4 2026 TU - A 93.5Moz silver project in NSW targets 26-year mine life, pending final permitting.SVL
Noosa Mining Conference 2026 - Strong cash position supports ongoing exploration and Bowdens Silver Project approvals.SVL
Q3 2026 TU - Advanced Bowdens Silver Project, improved loss, secured $30.2M funding, and faced legal setback.SVL
H2 2024 - Bowdens Silver Project advances toward development as capital raising and US expansion strengthen outlook.SVL
H2 2025 - Loss narrowed, capital raised, and Bowdens Silver Project advanced amid regulatory progress.SVL
H1 2026 - Bowdens advances as a top silver project, with DFS and permitting milestones expected in 2024.SVL
RIU Explorers Conference 2026 - Fully funded, advancing a top global silver project with new California exploration set for 2025.SVL
2025 Precious Metals Summit - Beaver Creek