Precious Metals & Critical Minerals Virtual Investor Conference
Logotype for Silverco Mining Ltd

Silverco Mining (SICO) Precious Metals & Critical Minerals Virtual Investor Conference summary

Event summary combining transcript, slides, and related documents.

Logotype for Silverco Mining Ltd

Precious Metals & Critical Minerals Virtual Investor Conference summary

14 Oct, 2026

Strategy and portfolio

  • Launched with a goal of building a silver producer exceeding 10 million oz/year within three years; two Mexican assets are targeted to be producing by the end of 2026.

  • La Negra is in Querétaro and Cusi is in Chihuahua; both are positioned in established mining regions with access to labor, infrastructure and services.

  • Share count was 54.4 million basic and ~61 million fully diluted; market cap was ~CAD 500 million and enterprise value just under CAD 450 million.

  • Victoria Avila became CFO at the end of September; Jesus Velador joined as VP Exploration, bringing more than 25 years of Mexico exploration experience.

Production and cash flow outlook

  • Forecast production growth exceeds 700% from H2 2026 to 2030, with 73% of revenue expected from silver.

  • Average annual production target is just under 6 million silver-equivalent oz; at $50/oz silver, forecast annual free cash flow is close to $80 million. Peak output exceeds 7 million oz and free cash flow is projected above $120 million/year.

  • La Negra is producing at 55% of its 2,500 t/day capacity; ramp-up to full commercial production is targeted by the end of H1 2027.

  • Cusi targets first concentrate in Q4 2026 and commercial production at 1,200 t/day by the end of H1 2027.

La Negra execution and economics

  • PEA at a $50/oz silver base case: after-tax NPV of $329 million, after-tax IRR of 131%, average annual production just over 4 million oz, AISC below $25/oz and an 8.2-year mine life.

  • Required funding at $50/oz is $12.5 million after expected La Negra cash flow over the next two quarters; funding need falls below $5 million at recent spot prices.

  • Approximately $20 million of capital improvements through H1 2027 are expected to be largely funded by cash flow; dry-stack tailings installation begins in Q1 2027 and commissioning is targeted in H1 2027.

  • New Epiroc equipment is expected to arrive over the coming weeks through Q1 2027; dry-stack capacity is intended to support throughput of 2,500 t/day.

  • Mine-plan work over the next 12 months may bring higher-grade zones planned for 2030 forward to as early as 2028; further opportunities include paste backfill and exploration.

Partial view of Summaries dataset, powered by Quartr API