19 Dec, 2025Project history and asset overview
Eskay Creek was previously the highest-grade gold mine globally, with historic grades of 45 g/t gold and over 2,000 g/t silver.
The asset was placed on care and maintenance in 2008, with a high cutoff grade of 15 g/t at the time.
Since 2017, the asset has been advanced with a focus on what remains below the historic cutoff.
The project is now being reconceptualized as a large-scale open-pit operation.
Expected annual production is 450,000 ounces of gold-equivalent metal, supported by robust grades.
Project economics and operational advantages
Projected open-pit grade is 5.5 g/t gold-equivalent, triple the global average.
Annual after-tax free cash flow is expected to be $1 billion for the first five years at current prices.
The project benefits from a fully permitted tailings facility, saving CAD 150 million in CapEx.
Access to hydroelectric power at CAD 0.06/kWh provides a significant cost advantage.
2023 DFS values the project NPV at CAD 5.5 billion at spot prices.
Permitting, partnerships, and community relations
The project is located in Tahltan territory, with a collaborative relationship and a historic Section 7 agreement.
Environmental assessment is in the final public engagement phase, concluding September 26.
Permits, including the EA certificate and Major Mines Act permit, are expected in Q4 2024.
The project is prioritized by the provincial government for fast-tracking due to its economic impact.
Latest events from Skeena Resources
- High-grade Eskay Creek mine nears production, promising strong cash flow and growth.SKE
Mining Forum Europe 202614 Apr 2026 - High-grade, low-cost gold-silver mine on track for 2027 production and strong cash flow.SKE
Corporate presentation13 Apr 2026 - Eskay Creek is on track for Q2 2027 production, offering top-tier gold and silver output with strong economics.SKE
Corporate presentation3 Apr 2026 - Eskay Creek targets Q2 2027 production, with strong economics and major milestones achieved.SKE
Kinvestor Mining & Energy Conference 202626 Mar 2026 - Eskay Creek advances toward Q2 2027 production, targeting top-tier gold-silver output.SKE
Q4 202525 Mar 2026 - High-grade gold-silver mine nears production with strong economics and robust community support.SKE
Corporate presentation23 Mar 2026 - High-grade, low-cost gold-silver project fully funded and targeting 2025 resource estimate.SKE
2024 Precious Metals Summit Beaver Creek21 Jan 2026 - Up to $525M in securities may be issued to fund Eskay Creek, with high risk and flexible capital use.SKE
Registration Filing29 Nov 2025 - High-grade Eskay Creek mine targets 2027 production with strong economics and expansion plans.SKE
Nordic Funds & Mines Conference 20259 Oct 2025