Tesoro Gold (TSO) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
10 Oct, 2026Project profile and economics
Single open-pit reserve of 1.28 Moz; 13-year mine life and planned 3 Mtpa processing plant.
PFS-based case: first nine years at 105,000–110,000 oz/year, AISC just under $1,600/oz, and upfront capital of $275m–$300m including pre-strip.
At $3,500/oz gold, post-tax NPV is around $1bn and IRR around 57%.
Site is 500 m above sea level, 13 km from the coast and Pan-American Highway, and 20–25 km from grid power and a desalination plant.
Development timetable and financing
DFS targeted by end-2026; final investment decision planned for Q1 2027.
EIA submission targeted for early 2027, with project approval targeted for early 2028; construction is expected to take 18 months, targeting first gold in late 2029.
Financing discussions with banks and other financiers are underway; indicative funding mix is 70% debt and 30% equity.
AUD 10m cash was expected to fund completion of the DFS and submission of permitting documentation.
Chilean permitting could take 12–14 months if applications cover requested surveys and avoid government information-request cycles.
Exploration and growth potential
120,000 m of infill drilling supported conversion of mineralization into a maiden reserve; management said results reinforced confidence in the resource model.
Near-mine targets aim to lift production to 120,000 oz/year or more by increasing grade, particularly over the first 10 years.
Drone Hill is a priority target west of Ternera, with potential to connect to the deposit; La Brea intercepts were described as similar to Ternera discovery holes.
Nine priority targets were identified along a 40 km mineralized belt; Pena Blanca, within 5 km of the planned plant, was preparing for drilling.
The deposit is an intrusion-related gold system described as a style not previously identified in Chile, with potential for further discoveries along the belt.
Latest events from Tesoro Gold
- Major resource upgrade at Ternera to 1.82Moz gold, with DFS and financing progressing.TSO
H1 2026 - DFS and drilling advanced at El Zorro, with A$15.29M cash and no debt at quarter end.TSO
Q4 2026 TU - DFS and major exploration progress position the project for development with strong economics.TSO
Noosa Mining Conference 2026 - El Zorro Gold Project advances toward feasibility with strong resource growth and robust economics.TSO
2025 Precious Metals Summit - Zurich - Major gold discovery, robust drill results, and A$9.7M raise drive project growth and de-risking.TSO
Q4 2024 TU - New gold discovery at Ternera East, strong cash position, and positive legal resolution.TSO
Q1 2025 TU - Strong exploration, robust cash, and direct advancement to DFS position the project for growth.TSO
Q3 2026 TU - Major exploration advances, improved loss, and strong capital raising position El Zorro for growth.TSO
H2 2024 - Resource up 42% to 2.0Moz, DFS underway, and A$45.1M raised for El Zorro's advancement.TSO
H2 2025