Tesoro Gold (TSO) Noosa Mining Conference 2026 summary
Event summary combining transcript, slides, and related documents.
Noosa Mining Conference 2026 summary
24 Jul, 2026Project advancement and development
El Zorro Gold Project in northern Chile is advancing toward a final investment decision, with the Ternera deposit undergoing DFS targeted for completion by year-end 2024.
The Ternera deposit hosts an in-pit resource of 1.18 million ounces, while the broader project features a 1.82Moz gold resource.
The project is supported by a strong management team, a strategic alliance with STRACON for integrated project delivery, and key partners for process plant and tailings facility design.
GR Engineering has designed a simple 3 Mtpa CIP processing plant using off-the-shelf equipment, with dry stack tailings and a focus on operational resilience.
Agreements are in place for water supply from a nearby desalination plant and renewable power, with a 21MW grid connection request and 90% of energy sourced renewably at competitive rates.
Exploration and resource potential
The deposit remains open to the north, south, and at depth, with significant upside potential through near-mine growth and district-scale discoveries across a 50km corridor.
Regional exploration campaign planned across a 670 sq km concession, targeting a 40-km corridor with multiple high-priority targets.
Two drill rigs are operating at Ternera East, aiming to expand the resource with promising initial results and high-grade intercepts.
Updated resource estimate expected within a month, aiming for over 85% indicated classification to support a maiden ore reserve.
Exploration team set to begin drilling new targets, with confidence in further discoveries along the belt.
Financials and capital structure
Ended last quarter with AUD 22 million cash, expecting AUD 15 million in the next quarter, funding all planned work.
Market capitalization is around AUD 150–160 million.
Gold Fields holds a significant stake, having invested AUD 13 million and participated in multiple placements.
Upfront capital costs for the project are expected to remain under $350 million despite design changes.
September 2025 Scoping Study indicates a post-tax NPV of US$663M and IRR of 51.3% at US$2,750/oz gold, with a 14-year mine life and 3Mtpa throughput.
Latest events from Tesoro Gold
- El Zorro Gold Project advances toward feasibility with strong resource growth and robust economics.TSO
2025 Precious Metals Summit - Zurich9 Jul 2026 - Major gold discovery, robust drill results, and A$9.7M raise drive project growth and de-risking.TSO
Q4 2024 TU3 Jun 2026 - New gold discovery at Ternera East, strong cash position, and positive legal resolution.TSO
Q1 2025 TU3 Jun 2026 - Strong exploration, robust cash, and direct advancement to DFS position the project for growth.TSO
Q3 2026 TU10 May 2026 - Major exploration advances, improved loss, and strong capital raising position El Zorro for growth.TSO
H2 202427 Mar 2026 - Resource up 42% to 2.0Moz, DFS underway, and A$45.1M raised for El Zorro's advancement.TSO
H2 202527 Mar 2026 - Chilean gold project targets 5Moz with strong economics and key infrastructure secured.TSO
2025 Precious Metals Summit - Beaver Creek3 Feb 2026 - Major drilling success and strong cash position support El Zorro’s development and exploration.TSO
Q2 2026 TU26 Jan 2026 - Scoping Study confirms strong economics and resource growth at El Zorro, with major funding secured.TSO
Q1 2026 TU27 Oct 2025